13.05.050 - Inspection, maintenance, record keeping, and reporting.
(a) Following approval of the stormwater management permit and commencement of construction activities, CBU shall have the authority to conduct inspections in accordance with Section 13.08.040(a) of the project site to ensure full compliance with this chapter, the City of Bloomington Stormwater Design Manual, and terms and conditions of the approved stormwater management permit, if applicable. (b) All erosion control measures shall be installed by the responsible parties and shall be inspected by CBU before any land-disturbing activity takes place. Any deficiencies noted by CBU during the initial inspection shall be remedied prior to land-disturbing activity commencing. (c) Throughout construction the responsible parties shall implement and follow a self-monitoring inspection program to ensure that their stormwater pollution prevention plan is working effectively and in accordance with the CSGP. At a minimum, the self-monitoring inspection program shall meet the requirements set forth in the City of Bloomington Stormwater Design Standards and shall require: (1) Periodic inspections of the project site by a trained individual: (A) At least one time per week; and (B) By the end of the next business day following each rain event of one-half inch of rain or more (as measured by the National Oceanic and Atmospheric Administration) in a twenty-four-hour period; and (2) Preparation of an evaluation report for every periodic inspection. Each evaluation report shall contain the following information: (A) Whether existing stormwater quality measures are being properly maintained and functioning properly; (B) Identify additional measures necessary to remain in compliance with all applicable laws and ordinances; and (C) The name of the individual performing the evaluation; (D) The date of the evaluation; (E) Problems identified at the project site; and (F) Details of corrective actions recommended and completed. CBU shall have the right to request complete records of maintenance and monitoring activities involving stormwater pollution prevention measures. All evaluation reports for the project site must be made available to CBU, in an organized fashion, within forty-eight hours upon request.
(Ord. No. 2024-08, § 1, 5-8-2024; Ord. No. 2025-24, § XIII, 7-30-2025)