§ 35-301 — Issuance of permit
Salina Code, City of Salina, Kansas (Codified through Ordinance No. 26-11299 adopted August 24, 2026. (Supp. No. 19)) · Salina Municipal Code § 35-301
Corpus is an independent public-information project, not the official City of Salina website. Stable reference: corpuslaw.us/code/4ea01df5-0b2c-4875-a243-7a62855c573d
Sec. 35-301. - Issuance of permit.
(a) The city shall process each valid and administratively complete application for a right-of-way permit within ten (10) business days. (b) The director of public works may, subject to applicable state and federal law, deny a permit or prohibit the use or occupancy of a specific portion of the right-of-way, or impose reasonable conditions upon the issuance of a right-of-way permit, to protect the public health, safety and welfare, to prevent interference with the safety and convenience of ordinary travel over the right-of-way, or when necessary to protect the right-of-way and its users. The director of public works may consider all relevant factors including but not limited to: (1) The extent to which the right-of-way space where the permit is sought is available; (2) The competing demands for the particular space in the right-of-way; (3) The availability of other locations in the right-of-way for the facilities of the applicant; (4) The applicability of any ordinance or other regulations that affect the location of facilities in the right-of-way; (5) The degree of compliance of the applicant with the terms and conditions of its franchise, this article, and other applicable ordinances and regulations; (6) The degree of disruption to the surrounding community and businesses that will result from the use of that part of the right-of-way; and (7) The balancing of costs of disruption to the public and damage to the right-of-way, against the benefits to that part of the public served by the construction in the right-of-way. (c) Issued permits are not transferable, except to an affiliate, parent or subsidiary that has registered with the city pursuant to section 35-395 of this article. (d) If permitted work is being done for a ROW-user by another person, a contractor, subcontractor, or otherwise, the person doing the work and the ROW-user shall be jointly liable and responsible for all damages, obligations, and warranties herein described. (e) Obtaining a right-of-way permit under this article shall not relieve a ROW-user of its duty to obtain any necessary permit, license, certification, grant, registration, franchise agreement or any other authorization required by any governmental entity, including, but not limited to, the city, the FCC or the KCC, or its duty to pay any fees required by any other city, county, state, or federal rules, laws, or regulations. (f) Right-of-way permits issued shall be conspicuously displayed at all times at the indicated work site and shall be available for inspection by the director of public works and the public.
(Ord. No. 14-10740, § 1, 7-28-14)
Ask a question about Salina law
Corpus searches the Salina sections it holds and shows the ones that match, with their citations. Free, no sign-in.