§ 243-59 — Road pavement replacement

Code of Ordinances, City of Lowell, Massachusetts · Lowell Code of Ordinances § 243-59

Corpus is an independent public-information project, not the official City of Lowell website. Stable reference: corpuslaw.us/code/e2e7b40a-e446-44a7-85ae-541e50751ce2

§ 243-59: Road pavement replacement.

A. Class A roadways in summer. (1) In the pavement area, the trench shall be backfilled with process gravel from a depth of 20 inches to four inches below the pavement grade and a four-inch bituminous concrete temporary patch laid for a period of 60 days. At this time the trench shall be excavated to a depth of eight inches. The pavement shall then be cut in a neat, true line at all vertical plane limits of the trench within the roadway and a six-inch slab of Class F, 3,500 psi, high early cement concrete constructed in the trench areas. The concrete is to set for 24 hours, at which time the pavement shall be restored with two inches of bituminous concrete Type I, consisting of a one-inch base course and a one-inch top course graded to meet the existing pavement. (2) Class A roadways shall be considered as main arteries in the City, state routes, roadways which fall under MGL c. 90 jurisdiction and any newly resurfaced roadway and any other roadway considered in Class A condition by the Commissioner of Public Works or his representative. B. Class A roadways in winter. In the pavement area, the trench shall be filled with suitable unfrozen material to a point 20 inches below roadway grade. Sixteen inches of process gravel shall then be placed over the compacted fill and four inches of temporary patch shall be placed and maintained by the utility or utility company for the remainder of the winter months. In the spring, when the ground is frost free, the trench shall be excavated to a depth of eight inches. The pavement shall then be cut in a neat, true line at all vertical plane limits of the trench within the roadway and a six-inch slab of reinforced Class F, 3,500 psi, high early cement concrete constructed in the trench areas. Reinforcing shall be No. 5 bars at six inches on center running in the direction of the trench. The bars shall be set a minimum of two inches above the lower limit of the concrete and no more than three inches above the same plane. After the concrete has set for 24 hours, the pavement shall be restored with two inches of bituminous concrete Type I, consisting of a one-inch base and a one-inch top course to meet pavement grade. C. Reinforced concrete pavement. If reinforced concrete pavement is encountered during repair work or installation of service laterals, reinforcing bars will be cut at the center and bent as necessary during the work. Patching procedure will be as described in Subsections A and B. When concrete is to be placed, bars will be bent to original position and the full depth of cement concrete pavement restored with high early strength air-entrained concrete. No burning or cutting out of reinforcing bars will be allowed. On new construction running longitudinally in roadway, reinforcing bars may be removed entirely from the excavation. Old bars may be reused if, in the opinion of the Commissioner of Public Works or his representative, they are serviceable, otherwise new reinforcing will be installed. The resetting or replacing of reinforcing bars will be made in accordance with acceptable construction standards.

Ask a question about Lowell law

Corpus searches the Lowell sections it holds and shows the ones that match, with their citations. Free, no sign-in.