4300. - ASPHALT PLANTS.

4310. Special Permit. No land located within an industrial "B" or industrial "C" zone shall be used for the operation of an asphalt or bituminous concrete processing plant, batching plant or a liquid asphalt storage facility unless a special permit for such use is granted by the City Council in accordance with the provisions of this Section. (a) Standard. In granting a special permit under this Section, the City Council shall consider the effects upon the neighborhood and the city at large. (b) Procedure. Before granting a special permit the City Council shall hold a public hearing thereon, within sixty-five (65) days from the date of filing of the application for special permit; notice of time and place of such hearing and the subject thereof, sufficient for identification shall be published in a newspaper of general circulation in the City of New Bedford once in each of two (2) successive weeks, the first publication to be not less than fourteen (14) days before the day of the hearing and also shall be sent by mail, postage prepaid, to the petitioner and to the owners of all property deemed by the City Council to be affected thereby as they appear on the most recent local tax list and to the Planning Board. Said notice shall also be posted in a conspicuous place in city hall for a period of not less than fourteen (14) days before the day of such hearing. (c) Issuance of permit. In granting any special permit provided for in this Chapter the City Council may issue said special permit subject to such appropriate conditions and safeguards as in its discretion will make an excepted use harmonious with the general purpose and intent of this Chapter. No special permit shall be granted under this Section except by a two-thirds (⅔) vote of the members of the City Council. A decision shall be made within ninety (90) days following the date of the public hearing.

(Ord. of 12-23-03, § 1)

Ask a question about New Bedford law

Corpus searches the New Bedford sections it holds and shows the ones that match, with their citations. Free, no sign-in.