§ 16-2.3 — Sewer extensions

Revised Code of Ordinances, City of Old Town Maine (eCode360 publication OL4196 current through legislation adopted 2025-12-01 (imported 2026-11-16)) · Revised Code of Ordinances, City of Old Town Maine § 16-2.3

Corpus is an independent public-information project, not the official City of Old Town website. Stable reference: corpuslaw.us/code/b4100fe0-5ad4-4f9d-b85f-f6d169837da2

§ 16-2.3: Sewer extensions.

(a) Construction; costs. (1) Public sewer extensions may be constructed by the City under public contract if, in the opinion of the City Council, the number of properties to be served by such extension warrants its cost. Under this arrangement the property owner shall pay for and install the building sewer from the public sewer to his residence or place of business in accordance with the requirements of § 16-2.2. (2) Property owners may propose sewer extension within the City by drafting a written petition, signed by a majority of the benefiting property owners, and filing it with the City Council. The cost of such extensions may be assessed to the benefited property owners in any manner determined by the City Council. (b) If the City does not elect to construct a sewer extension under public contract, the property owner, builder or developer may construct the necessary sewer extension, if such extension is approved by the City Council in accordance with the requirements of Subsection (d) below. He or they must pay for the entire installation, including all expenses incidental thereto. Each building sewer must be installed and inspected as previously required, and the inspection fee shall be paid therefor. Design of sewer shall be as specified in Subsections (d) and (e) below. The installation of the sewer extension shall be subject to periodic inspection by the Superintendent, and the expenses for this inspection shall be paid for by the owner, builder or developer. The Superintendent's decisions shall be final in matters of quality and methods of construction. The sewer, as constructed, must pass testing as required in Subsection (f) below before it is to be used. The cost of a sewer extension thus made shall be absorbed by the developers or the property owners, including all building sewers. All testing of new sewers must be performed in accordance with the provisions of this Part by a reputable entity routinely employed in the performance of such testing. (c) All extensions of public sewers constructed at the expense of the property owner, builder or developer, after approval and acceptance by the Superintendent, shall become the property of the City and shall thereafter be maintained by the City. Said sewers, after their acceptance by the City, shall be guaranteed against defects in materials or workmanship for 18 months. The guarantee shall be in a form provided for by the City. At the sole discretion of the City, a completion bond or certified check may be demanded as part of the guarantee. (d) Design. (1) All extensions to the sanitary sewer system owned and maintained by the City shall be properly designed in accordance with Guides for the Design of Wastewater Treatment Works, New England Interstate Water Pollution Control Commission Manual TR-16. (2) Plans and specifications for sewer extensions shall be submitted to and approval obtained from the Superintendent before construction may proceed. (3) The design of sewers must anticipate and allow for flows from all possible future extensions or developments within the immediate drainage area. (e) Sewer design shall be in accordance with the requirements of the building and plumbing code or other applicable rules and regulations of the City and DEP and the following provisions: (1) Pipe material shall be polyvinylchloride (PVC) SDR 35. (2) Minimum internal pipe diameter shall be eight inches. (3) Gaskets shall be continuous, solid and natural or synthetic rubber and shall provide a positive compression seal in the assembled joint. (4) Joint preparation and assembly shall be in accordance with the manufacturer's recommendations. (5) Wye branch fittings shall be installed for connection to building sewers or as required by the Superintendent. (6) Manholes shall be constructed at all changes in slope or alignment or at intervals not exceeding 300 linear feet, unless otherwise allowed by the Superintendent. The manholes shall be constructed with a poured 4,000 psi concrete base eight inches thick, steel-troweled concrete or mortar bench walls and brick inverts, and precast four-foot-diameter concrete manhole barrel sections with tapered top sections, as specified by A.S.T.M. C-478. The manhole frame and cover shall be set with no less than two nor more than five courses of brick underneath to allow for later adjustment in elevation. All joints shall be sealed against infiltration. External rubberized seals must be provided for all manholes unless otherwise approved by the Superintendent. (f) Testing. (1) All public sewers shall satisfy requirements of a final exfiltration test before they will be approved and sewage flow accepted from them by the City. This test shall be conducted pneumatically (air pressure test). (2) The pneumatic test consists of blanking both ends of the pipe with air locks and introducing air through a mechanism in one of the air lock units to a minimum stabilized pressure of 3.5 pounds per square inch greater than the groundwater pressure. Groundwater is assumed to be at ground surface unless otherwise proved by the contractor by test pitting. With a known permeability of the pipe, the only variable is the pipe diameter, and the minimum allowable time in minutes for a 1.0 pound per square inch pressure drop is found by multiplying the pipe diameter in inches by 0.472. (3) If leakage exceeds the specified amount, the necessary repairs or replacements required shall be made to permanently reduce the leakage to within the specified limit. (4) The City reserves the right to perform an internal television inspection as a part of the testing procedure. (g) No builder or developer shall be issued a building permit for a new dwelling or structure requiring sanitary facilities within the City unless a suitable and approved method of waste disposal is proposed. All new developments shall be provided with an approved system of sanitary sewers.

[ Ord. of 5-5-2008 ]

Ask a question about Old Town law

Corpus searches the Old Town sections it holds and shows the ones that match, with their citations. Free, no sign-in.