§ 17-69 — Procedures for trenching and backfilling
Revised Code of Ordinances, City of Old Town Maine (eCode360 publication OL4196 current through legislation adopted 2025-12-01 (imported 2026-11-16)) · Revised Code of Ordinances, City of Old Town Maine § 17-69
Corpus is an independent public-information project, not the official City of Old Town website. Stable reference: corpuslaw.us/code/38294446-b50e-4b76-91b7-c3d1fa349f79
§ 17-69: Procedures for trenching and backfilling.
(a) Backfilling. The trench or opening shall be backfilled with the same material that was removed from the trench to within 18 inches of the existing pavement except as may be hereinafter provided. The top 18 inches of the trench shall be filled with approved five inch minus gravel; provided, however, that not more than 18 inches of gravel is under existing pavement. In this latter event an equal amount must be replaced. If a permit is issued during the winter time the excavated material shall be removed and replaced, this frozen material shall not be replaced in the trench but shall be removed from the area and disposed of and the excavated area backfilled with excavation grade flowable fill. If the material excavated contains too much moisture for proper compaction, it shall be removed and replaced with suitable backfill material. (b) Tamping backfill. All backfilling shall be thoroughly tamped or compacted either by hand tamping or power tampers. The first six inches of fill over the structure or pipe in the trench shall be hand tamped. The balance of the filling shall be thoroughly tamped and, if powered hand tampers are used, the backfill material may be placed in 10 inch layers and thoroughly compacted. Puddling of the backfill will not be permitted except by special permission from the director or his designated person. All backfill shall meet at least 95% of total compaction as measured by modified Proctor test and submitted to public works director or appointed individual. Testing shall be done and documented by modified proctor test every 18 inches of depth to include one at the surface and every 50 feet of trench length. The contractor (permitted) also reserves the right to use an excavation grade flowable fill of 95% on placement in lieu of excavated material. If flowable fill is used for entire backfill modified proctor testing and documentation would be waived. If flowable fill is used to backfill any pipe water valve or other relative utilities first must have at least 12 inches of compacted sand placed over the top of utility and flowable fill placed to the bottom of the surface material. The permitted opening must then be protected for not less than 12 hours after being placed. And the surface material placed immediately following. There will be no surface paving done in temperatures below 40° F. unless the Director has given prior approval.
[ Ord. of 4-16-1973 ; Ord. of 6-2-2003 ]
Ask a question about Old Town law
Corpus searches the Old Town sections it holds and shows the ones that match, with their citations. Free, no sign-in.