Sec. 24-54. Demolition of buildings.
(a) No building served by a building drain or sewer which is connected to the public sewers or to a private sewer system connected to the public sewers, may be demolished prior to the termination of the building sewer or drain at the public sewer under the inspection of the Department of Public Works. The building sewer shall be terminated at the main, at the point designated by the Department of Public Works. (b) Notice of intent to demolish a building shall be given to the Department of Public Works, by means of a copy of the application for a demolition permit from the building authority or by direct notice to the Department of Public Works, in advance of the time when the building drain or sewer is to be terminated. No such demolition permit shall be issued until a drain termination permit has been issued by the Department of Public Works and a copy thereof has been given to the building authority. (c) The fee to terminate the building and/or facility sewer and/or drain system will be paid to the city in advance of the termination. The fee of two hundred fifty dollars ($250.00) per termination represents inspection fees and materials to terminate sewer service. Upon payment of this fee and approval by the Department of Public Works, the applicant shall be issued a sewer termination permit. (d) Failure to give notice of intent to demolish a building to the Department of Public Works, or to terminate the building drain prior to demolition thereof, or to obtain a permit therefor, shall be deemed a violation of this section, with each day in which the violation continues deemed to be a separate violation. (e) All excavation for sewer service termination shall be made and maintained in compliance with all provisions of the construction safety rules and regulations of chapter 25, article VII of this Code. (f) Violations. The property owner who fails to obtain a sewer termination permit and terminate the sewer or drain from the building to be demolished to the public sewer shall be guilty of an offense. (g) Failure to comply. When a person to whom an order is directed fails to terminate a building sewer or drain within a ten-day period, it shall be lawful for the city to terminate the building sewer or drain. All city costs thereof shall be charged to the property owner.
(Ord. No. 263-96, 5-20-96; Ord. 129-14/15, 1-21-2015, Effective 1-1-2016)
Ask a question about Portland law
Corpus searches the Portland sections it holds and shows the ones that match, with their citations. Free, no sign-in.