Sec. 29.5-75. - Permit applications for right-of-way construction or engineering permit.
(a) Applications for a right-of-way permit under article II of chapter 26 of the Code and the standards and regulations in this article shall be filed with the engineering division of the department of public services and shall include plans for the proposed wireless facilities, wireless support structures, and utility poles in a quantity, form, size, and scale required by the engineering design standards for site development and redevelopment, with the engineering division allowed to waive or relax a standard to the extent it is not applicable or necessary for review of the application. The plans shall include a cover sheet with the project name, wireless provider applicant name and contact information, a general location map and sheet index, and detailed scaled location and elevation drawings for each site for which the permit is requested that show, describe, and include the following: (1) The sides and specific locations on named streets, with geographic information system (GIS) coordinates. (2) The location and edges of the public right-of-way and portion used for vehicular travel, and the location and dimensions of existing above-ground structures, utilities, sidewalks, driveways, buildings, signs, traffic lights and signs, poles, curbs, buildings, utility cabinets, utility pole guy wires, shelters, benches, storm drains, wireless support structures, utility poles, other improvements, and trees within seventy-five (75) feet of the proposed location. (3) Existing below ground structures including but not limited to water, sanitary sewer, storm sewer, electric, gas, cable, communication lines, and conduit. (4) Information necessary to demonstrate compliance with the public, utility, and traffic safety and protection standards in section 29.5-76. (5) Information necessary to demonstrate compliance with the aesthetic, spacing, and undergrounding standards in section 29.5-77. (6) Information necessary to demonstrate compliance with the applicable standards for the type of wireless facilities, support structure, or utility poles for which approval is requested under sections 29.5-78 through 29.5-82. (b) In addition to identification of the type of proposed wireless facility and applicable Code section as required in section 29.5-74(b) and the plans described in subsection (a), applications shall include: (1) Certified documentation that each proposed wireless support structure or utility pole can structurally accommodate the proposed wireless facilities and documentation of its ability to accommodate the proposed and any future wireless facilities. (2) Manufacturer, model number, height, width, depth, weight, and volume in cubic feet of all proposed wireless facilities individually and collectively, specifically including the total cubic feet of each antenna and the total cubic feet of all other wireless facilities. (3) The identity of the wireless provider applying for the permit and the owners of and wireless providers that will use the wireless facilities, wireless support structures, and utility poles for which the permit is requested, and for each of those entities the following: a. Legal and any assumed names, and resident agent name, if any. b. Local, mailing, and registered office addresses. c. Name, title, and authority of signatory for that entity. d. Contact person name, address, phone numbers and email address. (4) Documentation that the owner of the proposed wireless facilities, wireless support structures, and utility poles has approved what is disclosed in the plans for the requested permit. (5) A written certification by the applicant that the wireless facilities for which the permit is requested will be operational within one (1) year after permit issuance. (6) A certificate of compliance with FCC rules related to radio frequency emissions from the proposed wireless facilities. (7) Copies of any required permits from other governmental entities that also have an ownership, control, or jurisdictional interest in the public right-of-way or documentation that those permits have been properly applied for. (8) Documentation of the date when complete applications for construction code permits and any required zoning ordinance permits or approvals were or will be made. (9) Identification of contractors who will be working in the public right-of-way and contact persons and information for those contractors. (10) A construction schedule indicating the period of time for the work from commencement to completion and restoration of all public right-of-way disturbed by the work. (11) A traffic control plan for when work is being performed in the public right-of-way. (12) Photo simulations of existing and proposed conditions. (13) A video recording of the location showing the staging and work areas where construction machinery will be driven or positioned off the traveled roadway. (14) Documentation of the applicant's ability to provide any required bond under section 29.5-85. (15) Payment of any application, review, or processing fee established by resolution of the city council under section 29.5-86. (16) For applications that would involve exceeding the height limits under Public Act No. 365 of 2018, to the height limits allowed by 47 CFR 16.001—16.003, a statement of whether the applicant agrees to payment of the annual recurring fees recognized as presumptively valid under the Declaratory Ruling and Order in FCC 18-133. (c) An application may be for up to twenty (20) collocations by the applicant of substantially similar small wireless facilities for placement on similar types of wireless support structures or utility poles.
(Ord. No. C-4-2019, § 1, 3-25-19)