Sec. 102-534. - Permit modification.
(a) Permit modification. The terms and conditions of the permit may be subject to modification by the department during the term of the permit as limitations or pretreatment standards and requirements identified in this article are amended, or other just cause exists. Just cause for a permit modification includes, but shall not be limited to, the following: (1) Material or substantial changes to an industrial user's facility or operation, or changes in the characteristics of the industrial user's effluent It shall be the industrial user's duty to request an application form and apply for a modification of the permit within 30 calendar days of the change; (2) Change(s) in the department's NPDES permit; (3) Embodiment of the provisions of a legal settlement or of a court order; (4) Any changes necessary to fulfill the department's role as control authority; (5) An industrial user's noncompliance with portions of an existing permit; (6) A change of conditions within the POTW; (7) A finding of interference or pass-through attributable to the industrial user; (8) Amendments to, or promulgation of, National Categorical Pretreatment Standards or requirements including 40 CFR Part 403 and those delineated in Appendix A of this article: a. Permittees shall request an application form and apply to the department for a modified permit within 90 days after the promulgation of a new or revised National Categorical Pretreatment Standard to which the industrial user shall be subject. b. Information submitted pursuant to this subsection shall be confined to that information related to the newly promulgated or amended National Categorical Pretreatment Standard or requirement. However, information previously submitted need not be duplicated, insofar as the previously submitted information continues to be current and applicable. c. In addition, the department may initiate this action. (9) Changes in the monitoring location; (10) Typographical errors or omissions in permits; (11) The department may modify the permit on its own initiative based on its findings or reasonable belief of the above; or (12) The user may request a modification of the permit. (b) When initiated by the department, the industrial user shall be informed of any proposed change in its permit. The department will issue a draft permit and an industrial user has 30 days to file a response to the draft modified permit. Thereafter, the department will issue a final permit and, unless appealed in accordance with the procedures contained in this article, the permit will become effective 20 days after issuance.
(Ord. No. 537, § 1, 7-13-2009)
Ask a question about Rochester Hills law
Corpus searches the Rochester Hills sections it holds and shows the ones that match, with their citations. Free, no sign-in.