Section 22.05 - Duration of permit.

In the event a building permit shall have been issued by the Building Department and no proceeding under authority thereof shall have been commenced by the applicant within six (6) months following the date of issuance, said permit shall lapse and become void and be ineffective as authority for acting thereunder unless, within ninety (90) days following such six (6) months' period the applicant shall apply for reinstatement thereof. The Building Director is hereby authorized to reinstate such permit, but no original building permit shall be reinstated more than once.

Ask a question about Warren law

Corpus searches the Warren sections it holds and shows the ones that match, with their citations. Free, no sign-in.