§ 22.15 — Performance guarantees
Code of Ordinances of the City of Warren, Michigan (Supp. No. 102: codified through Ordinance No. 80-840, adopted October 28, 2025) · Warren City Code § 22.15
Corpus is an independent public-information project, not the official City of Warren website. Stable reference: corpuslaw.us/code/40ff8e2e-a993-42d5-b144-d3cabe04f14a
Section 22.15 - Performance guarantees.
A. To insure compliance with this Ordinance and any conditions imposed hereunder, an approving authority as provided for in this ordinance may require that a cash deposit, certified check, or surety bond acceptable to the City covering the estimated cost of improvements associated with the project for which site plan approval is sought be deposited with the City Treasurer to insure faithful completion of the improvements within two (2) years. The amount of the bond or deposit shall be determined by the approving authority and shall be based upon a reasonable estimate of the cost of all improvements on the site. The performance guarantee shall be deposited at the time of the issuance of the permit authorizing the activity or project. The deposit of the performance guarantee shall not be required prior to the time when the City is prepared to issue the permit. B. As used in this Section "improvements" means those features and actions associated with the project which are considered necessary by the approving authority to protect natural resources, or the health, safety, and welfare of the residents of the City and future users or inhabitants of the proposed project or project area, including roadways, lighting, utilities, sidewalks, screening, and drainage. Improvements does not include the entire project which is the subject of site plan approval. C. Any performance guarantee required as per this ordinance shall continue until such time as the City notifies the surety that the conditions imposed upon the development have been met. The bond will not be approved by the City, unless this provision is specifically set forth in bold type within the bond. The release of the site plan bond shall be done in conjunction with the release of the building permit bond. Inasmuch as the two bonds are related to the overall development, the approving authority will not release the site plan bond until the Building Department and approving authority are satisfied that the site is developed in accordance with the site plan approval.
(Ord. No. 30-657, § 10, 4-12-83)
Ask a question about Warren law
Corpus searches the Warren sections it holds and shows the ones that match, with their citations. Free, no sign-in.