Sec. 11.050. - Application—Contents and submission requirements.
A. Administrative process for conditional and accessory uses. The following items shall be submitted in support of an application for building permit for (a) micro or small wind turbine(s): 1. Signed and notarized affidavits from all property owners who have a shared lot line with the applicant and consent to the proposed wind turbine. If a property owner sharing a lot line with the applicant does not consent to the proposed wind turbine, the use shall not be allowed as a conditional use. The applicant may proceed with an application for a special use permit. (For conditional use only.) 2. A plot plan, utilizing a standard engineering scale not to exceed 1:100, indicating the placement of the wind turbine(s) and distances from the proposed turbine location to the nearest built structure, any above ground utilities, the nearest tree(s), and all property lines. 3. Turbine information: Specific information on the type, model, size, height, rotor material, rated power output, performance, safety, and noise characteristics of each wind turbine being proposed, tower and electrical transmission equipment. 4. Data in sufficient detail to allow for a determination that the proposed WECS shall meet all the aforementioned standards. 5. Drawings of the wind turbine structure, including the tower, base, and footings. In addition, an engineering analysis of the tower showing compliance with the International Building Code certified by a licensed professional engineer. 6. Building permit applications for micro or small wind energy systems shall be accompanied by a line drawing of the electrical components in sufficient detail to allow for a determination that the manner of installation conforms to the adopted National Electrical Code (NEC). All building permits require installations to be designed and sealed by an engineer licensed in the State of Missouri, designs shall include structural analysis. B. Special use permit process. The following items shall be submitted in support of a special use permit application for (a) large/utility scale wind turbine(s): 1. All plan submission requirements of Sections 2.300 and 6.630. 2. The site plan shall include the distance from the proposed turbine location to the nearest built structure, any above ground utilities, the nearest tree(s), and all property lines. 3. The proposed location and design of the wind facility, including all turbines, ground equipment, appurtenant structures, transmission infrastructure, access, fencing, exterior lighting, etc. 4. Turbine information: Specific information on the type, model, size, height, rotor material, rated power output, performance, safety, and noise characteristics of each wind turbine being proposed, tower, and electrical transmission equipment. 5. A noise study, prepared by a qualified professional, shall demonstrate that except for during short-term events such as utility outages and severe windstorms, the large/utility scale wind turbine shall not produce noise in excess of 55 dbA at the property lines. The noise study shall include: a. A description and map of the project's noise producing features, including the range of noise levels expected, and the basis for such expectations. b. A description and map of the noise sensitive environment, including any sensitive noise receptors (e.g. residences, hospitals, libraries, schools, places of worship, parks, areas with outdoor workers and other facilities where quiet is important or where noise could be a nuisance) within 1,000 feet. c. A survey and report prepared by a qualified engineer that analyzes the pre-existing ambient noise (including seasonal variation) and the affected sensitive receptors located within 1,000 feet. d. A description and map of the cumulative noise impacts. e. A description of the project's proposed noise control features and specific measures proposed to mitigate noise impacts for sensitive receptors as identified above to a level of insignificance. 6. Soil. A geotechnical report shall be furnished along with the certification which shall, at a minimum, include the following: a. Soils engineering and engineering geologic characteristics of the site based on on-site sampling and testing. b. Foundation design criteria for all proposed structures. c. Slope stability analysis. d. Grading criteria for ground preparation, cuts and fills, and soil compaction. 7. Shadow/flicker. A shadow/flicker model shall demonstrate that shadow/flicker shall not fall on, or in any existing residential structure. The shadow/flicker model shall: a. Map and describe within a 1,000-foot radius of the proposed wind energy system the topography, existing residences and location of their windows, locations of other structures, wind speeds and directions, existing vegetation and roadways. The model shall represent the most probable scenarios of wind constancy, sunshine constancy, and wind directions and speed; b. Calculate the locations of shadow/flicker caused by the proposed project and the expected durations of the shadow/flicker at these locations, calculate the total number of hours per year of shadow/flicker at all locations; c. Identify problem areas where shadow/flicker will interfere with existing or future residences and roadways and describe proposed mitigation measures, including, but not limited to, a change in siting of the wind energy conversion system, a change in the operation of the wind energy conversion system, or grading or landscaping mitigation measures. 8. Impact on wildlife. A study shall be provided by a professional that demonstrates that the development and operation of the wind turbine(s) in question shall not have an adverse impact on endangered or threatened avian or bat species and their critical habitats. 9. The Director, Commission, or Governing Body may require additional technical studies deemed necessary to fully evaluate the application. Should the services of an outside consultant be needed to evaluate any such technical studies, the cost of such services shall be borne by the applicant.
Ask a question about Lee's Summit law
Corpus searches the Lee's Summit sections it holds and shows the ones that match, with their citations. Free, no sign-in.