Sec. 2.380. - Expiration of an approved final development plan.
Final development plan approval shall not be valid for a period longer than 12 months from the date of such approval, unless within the period a building permit is obtained and substantial construction is commenced and all additional building permits necessary to complete the project as approved in the final development plan schedule are obtained in a timely fashion, as determined by the Code Official. The Director of Development Services may grant one extension of no more than 12 months each upon written request of the original applicant. An application for extension of a final development plan may be granted, if the application is filed before the final development plan expires. Upon granting an extension, the Director has the authority to attach new conditions to the final development plan, as deemed appropriate. Further extension requests shall require approval by the Governing Body. Upon granting an extension, the Governing Body has the authority to attach new conditions to the final development plan, as deemed appropriate.
(Ord. No. 10040, § 4(Exh.), 12-17-2024)