§ 700.560 — New Or Extended Water And Sewer Mains

Code of Ordinances, City of O'Fallon, Missouri (Code 2026-10-22) · O'Fallon City Code § 700.560

Corpus is an independent public-information project, not the official City of O'Fallon website. Stable reference: corpuslaw.us/code/a8aff21f-e716-420d-a8e8-beff5d5bc826

Section 700.560: New Or Extended Water And Sewer Mains.

A. Applications for new or extended water and sewer mains by any person, firm, corporation, partnership, etc., shall be made in writing to the City and such applications shall be accompanied by three (3) copies of the plan and three (3) copies of the estimated construction costs as prepared by the applicant's engineer for the tract of land to which or in which such new or extended water or sewer main is requested, showing streets, alleys, easements, property lines and the proposed locations of water lines, and all proposed connections thereto. All applications for water taps or connections to water mains and extensions and/or sewer taps or connections, shall be in writing and accompanied by a drawing showing location of main or extension and the location of the proposed connection to the main or extension. The City shall charge the applicant a fee for water and sewer connections or tap-ons as provided herein. B. Prior to the construction of any main or extension, the applicant shall be required to enter into an escrow agreement with the City, controlled by an escrow agent, totaling the estimated cost of construction of such main or extension and connection thereto. Following completion of construction and inspection as provided herein, and upon approval by the City, the City shall authorize release of the applicants escrow. If the applicant fails to complete the construction within two (2) years, the City reserves the right to retain or expend all or any portion of the escrow to complete construction and/or bring said construction up to acceptable standards. If applicant believes he/she can justify the need to extend the project for an additional year, a written request shall be made to the City sixty (60) days before the end of the original two (2) year period. The City may extend said construction period an additional year if, in the City's opinion, such extension is justified. C. All water and sewer mains and extensions thereof constructed or installed under the provisions of this Chapter shall be inspected by the City and are subject to repairs and corrections as outlined in this Chapter herein and as deemed necessary by the City. All water and sewer mains and extensions thereof constructed or installed under the provisions of this Chapter shall be and remain the property of the City in consideration of their perpetual upkeep and maintenance with no compensation being paid to the applicant. The City reserves the right to further extend and connect to any water or sewer main or extension. D. The pipe used in making water and sewer extensions shall be of a type and size which will be compatible with the City's plans for total development of the area. Such determination as to size and type of pipe shall be solely up to the judgement of the City, as determined by the City Engineer. The City as determined by the City Engineer reserves the right to determine the size and type of pipe based upon the City's long range water and sewer use plan. If the City desires to make the extensions larger than required to provide service to the lots abutting said extension, the additional cost due to such larger size shall be borne by the City. All added costs will be determined in advance of construction and be based upon an agreement entered into by the City and the applicant prior to construction commencing. E. Credit For Off-Site Extensions Or Improvements. 1. The City may, at its sole discretion enter into agreement with the applicant to waive connection fees for line extensions up to an amount equal to the actual construction cost of the off-site line extensions(s) or improvement(s). "Off-site line extensions or improvements" are defined as extensions or improvements needed and constructed to bring service to a development and does not include any improvements to distribution mains or collector sewers within a development. 2. In cases where the construction cost of off-site extension(s) or improvement(s) exceed the connection fees for that particular development, no additional connection fee credit will be given. Construction costs will include the necessary size line as determined by the City and the responsibility of acquiring easements will be the responsibility of the applicant. Construction costs will not include costs of obtaining and dedicating necessary easements to the City. 3. Providing that the City and applicant enter into an agreement providing for waiver of connection fees, the applicant will provide the City with copies of all invoices related to the off-site extensions or improvements, understanding that the material and construction costs are subject to verification by the City. F. Upon completion of construction of the water and/or sewer extensions and approval of construction by the City, applicant shall dedicate the extensions(s) and all necessary easements for proper maintenance and repair of the extension(s) to the City at no cost to the City. At such time the applicant shall submit the following to the City. 1. One (1) reproducible mylar and three (3) copies of as-built plans including certification of construction by the design engineer. 2. Easement deed or record plat showing appropriate easements dedicated for City use. 3. Copy of appropriate lien waiver. G. The City shall have the right to inspect and require any appropriate test of any extension prior to connection to a City main line. The actual connection shall be inspected and approved by the City. The City shall not be liable to provide service until such time as all fees have been paid and the extension(s) have been approved and accepted by the City. H. Applicants constructing water and/or sewer main extensions, booster pump station, water well, lift station or other such structure shall provide escrow funds in the amount of ten percent (10%) of the structure(s) cost for a one-year period after completion of construction. This one-year period shall be considered a warranty period to ensure construction was in accordance with plans, specifications and maintenance of the structure, with the applicant making any necessary repairs or corrections.

[R.O. 2008 § 700.560; R.O. 2007 § 700.560; Ord. No. 1810 Art. II § 1, 4-17-1990 ; Ord. No. 3049 § 1, 8-5-1993 ; Ord. No. 3249 § 1, 6-20-1995 ]

Ask a question about O'Fallon law

Corpus searches the O'Fallon sections it holds and shows the ones that match, with their citations. Free, no sign-in.