Sec. 36-148. - Required inspections and testing.

Construction or work for which a permit is required shall be subject to the following inspections by the building official and such construction or work shall remain accessible and exposed for inspection purposes until approved. Approval as a result of an inspection shall not be construed to be an approval of a violation of the provisions of these codes or of other ordinances of the jurisdiction. No inspection, nor any interpretation of such inspection, may authorize the violation, or cancellation of, the provisions of these codes or of other ordinances of the city. It shall be the duty of the person or contractor to whom a permit has been issued to cause the work to remain accessible and exposed for inspection purposes. Neither the building official nor the jurisdiction shall be liable for expense entailed in the removal or replacement of any material required to allow inspection. (1) Footing or foundation inspection. Footing and foundation inspections shall be made after excavations for footings are complete, after poles or piers are set, or trenches or basement areas are excavated and any required reinforcing steel is in place. Prior to placement of any concrete, for concrete foundations, any required forms shall be in place prior to inspection. The footing/foundation inspection shall include excavations for thickened slabs intended for the support of bearing walls, partitions, structural supports, or equipment, and special requirements for wood foundations. Materials for the foundation shall be on the job, except where concrete is ready mixed in accordance with ASTM C 94, the concrete need not be on the job. (2) Concrete slab or under-floor inspection. Concrete slab and under-floor inspections shall be made after in-slab or under-floor reinforcing steel excluding floor wire mesh reinforcement and building service equipment, conduit, piping accessories, and other ancillary equipment items are in place and approved, but before any concrete is placed or floor sheathing installed, including the sub-floor. (3) Lowest floor elevation. In flood hazard areas, upon placement of the lowest floor, including the basement, and prior to further vertical construction, the elevation certification required by the currently adopted building and residential codes, shall be submitted to the code official. The lowest floor elevation shall be as required in General Ordinance No. 5907 of the City of Springfield. (4) Stem wall inspection. A stem wall inspection shall be required at such time as all forms are set and reinforcement is in place. Stem wall forms shall be marked in such a manner as to denote the "top of wall." Concrete masonry unit foundation walls shall be inspected at such time as the top course has been installed and prior to any further vertical construction has taken place. (5) Floor framing inspection. Where framed floors are constructed over crawl spaces without a minimum vertical clearance of 32 inches from the bottom of floor joists to bottom surface of the crawlspace, and without a minimum vertical clearance of 18 inches from bottom of girders to bottom surface of crawlspace, a floor framing inspection shall be required before the floor framing is completely covered by subflooring and flooring. Until the floor framing is inspected and approved the subflooring and flooring shall remain uninstalled at each of the following and at two separate locations of each condition to allow access and inspection: a. Corner foundation anchor bolts; b. Girder to pier shim conditions; c. Girder to foundation pocket; d. Minimum of eight linear running length of foundation wall with typical anchor bolt installation. (6) Blocking and sheathing inspection. Blocking and sheathing shall be inspected prior to installation of any material that will conceal blocking or sheathing from view, and prior to frame and masonry inspection. (7) Frame and masonry inspection. Framing and masonry inspections shall be made after the roof deck or sheathings, masonry, all framing, fire-blocking, fire-stopping, draft-stopping, and bracing are in place and pipes, chimneys, and vents to be concealed are complete and after the rough-in inspections are approved for the area inspected. (8) Building envelope insulation and sealing inspection. Insulation and sealing of the building envelope shall be inspected on projects governed by the adopted International Residential Code before installation of finishes or any element that will cover the sealing and insulation work and prevent inspection. If building construction fails to meet the requirements of the approved drawings and codes and the contractor does not correct the deficiencies the building inspector has the authority to require building envelope and duct leakage testing. (9) Fire- and smoke-resistant penetrations. Protection of joints and penetrations in fire-resistance-rated assemblies shall not be concealed from view until inspected and approved. (10) Fire-resistance-rated construction inspection. Where fire-resistance-rated construction is required, the building official shall require an inspection of such construction after all lathing and/or wallboard is in place, but before any plaster is applied, or before wallboard joints and fasteners are taped and finished. (11) Inspections and testing of systems. Systems shall include, but are not necessarily limited to, mechanical, electrical, plumbing, fire suppression, and fuel gas systems. The building official, upon notification from the permit holder or the permit holder's agent, shall make the following inspections and other such inspections as necessary, and shall either release that portion of the construction or shall notify the permit holder or the permit holder's agent of violations that must be corrected. The holder of the permit shall be responsible for the scheduling of such inspections. a. Service utilities. 1. Connection of service utilities. No person shall make connections from a utility, source of energy, or a fuel or power source to any building or system that is regulated by this code for which a permit is required, or until released by the building official. 2. Temporary connection. The building official shall have the authority to authorize the temporary connection of the building or system to the utility source of energy, or fuel or power source. b. Underground and sub-slab system inspection. Underground and sub-slab system inspections shall be made after trenches or ditches are excavated and bedded, piping installed, and before backfill is put in place. When excavated soil contains rocks, broken concrete, frozen chunks and other rubble that would damage or break the piping or cause corrosive action, clean backfill shall be on the job site. c. Rough-in system inspection. Rough-in inspection shall be made after the roof, framing, fire-blocking, and bracing are in place and all ducting and other components to be concealed are complete, and prior to the installation of wall or ceiling membranes. d. Final system inspection. Final inspection shall be made upon completion of the system. Exception: Ground-source heat pump loop systems tested in accordance with Section 1208.1.1 of the International Mechanical Code shall be permitted to be back-filled prior to inspection. The requirements of this section shall not be considered to prohibit the operation of any heating equipment or appliances installed to replace existing heating equipment or appliances serving an occupied portion of a structure provided that a request for inspection of such heating equipment or appliances has been filed with the department not more than 48 hours after such replacement work is completed, and before any portion of such equipment or appliances is concealed by any permanent portion of the structure. e. Final building inspection. The final building inspection shall be made after all work required by the building permits is completed. f. Other inspections. In addition to the inspections specified above, the building official is authorized to make or require other inspections of any construction work to ascertain compliance with the provisions of this code and other laws that are enforced by the department of building development services.

(Ord. No. 6352, § 5, 3-20-17; Gen. Ord. 6553, § 1, 11-18-19)