§ 98-53 — Work restoration—Required
Code of the City of Springfield, Missouri (Supp. No. 23, Update 2: codified through G.O. No. 6973, enacted January 12, 2026) · Springfield, Mo., City Code § 98-53
Corpus is an independent public-information project, not the official City of Springfield website. Stable reference: corpuslaw.us/code/5aa5d563-a4da-47d9-8279-cfa2c75c49db
Sec. 98-53. - Work restoration—Required.
(a) At the completion of any work requiring excavation within a right-of-way, such excavation shall be immediately restored by backfilling and repairing all areas that were disturbed or damaged by the work in accordance with this article and the rules promulgated by the director. (b) If excavation cannot be restored immediately and is left unattended, the permittee shall securely and adequately cover and mark the unfilled/unrepaired excavation. The permittee has sole responsibility for maintaining proper temporary traffic control, barriers, safety fencing, signage, and/or lights as required, from the time of the opening of the excavation until the excavation is surfaced and opened for travel. (c) The director is authorized to promulgate rules and regulations for restoration consistent with the city's standard specifications for construction of streets, sidewalks and other paved areas of property owned by the city. The back filling of all excavations in, through, or under the paved areas of property, right-of-way and easements owned by the city shall be subject to those standard specifications and the following requirements: (1) If the edge of the excavation is within three feet of the edge of the roadway, or joint in the pavement, or edge of an existing repair or street patch, the permittee must extend the repair, including the paving and its aggregate foundations, to the edge of the roadway, or joint in the pavement, or edge of an existing repair or street patch street. (2) A right-of-way user shall remove all surplus earth, rock or rubbish from the excavation site and clean the excavation site and surrounding area affected by the excavation within 24 hours after the back fill has been completed. (d) Unless the city elects to restore the right-of-way itself as permitted in this article, every right-of-way user shall guarantee for a period of four years the restoration of the right-of-way in the area where such right-of-way user conducted excavation work and performed the restoration.
(G.O. No. 6966, § 1(Exh. A), 12-15-2025)
Ask a question about Springfield law
Corpus searches the Springfield sections it holds and shows the ones that match, with their citations. Free, no sign-in.