§ 98-54 — Failure to restore
Code of the City of Springfield, Missouri (Supp. No. 23, Update 2: codified through G.O. No. 6973, enacted January 12, 2026) · Springfield, Mo., City Code § 98-54
Corpus is an independent public-information project, not the official City of Springfield website. Stable reference: corpuslaw.us/code/ce600308-3d9a-46f4-ae4d-ec075c367e0f
Sec. 98-54. - Failure to restore.
(a) If the right-of-way user fails to restore the right-of-way in the manner and to the condition required by the director, or fails to satisfactorily and timely complete all restoration, the city may, at its option, serve written notice upon the right-of-way user and its surety that, unless within ten days after serving of such notice, a satisfactory arrangement is made for the proper restoration of the right-of-way, the city shall immediately serve notice of failure to comply upon the surety and the right-of-way user, and the surety shall have the right to arrange for and complete the restoration excavation or work; provided, however, that if the surety does not commence performance thereof within 14 days from the date of notice, the city may perform its own restoration excavation or work and prosecute same to completion, by contract or otherwise. (b) Upon determination by the director that the failure to repair, replace, or restore creates a threat to public safety, or the excavation includes open cutting of the surface of a street classified as a collector or higher, all such repair or replacement shall be corrected within 24 hours of notice from the city, or the city will perform its own repair, replacement, or restoration. (c) Upon determination by the director that the failure to repair, replace, or restore creates an immediate threat to public safety, or the excavation includes open cutting of the surface of a street classified as a primary arterial or higher, all such repair or replacement shall be corrected within one hour of notice from the city, or the city will perform its own repair, replacement, or restoration. (d) The right-of-way user and its surety shall be liable to the city for its actual costs of such repair, replacement, or restoration, including the value of any time or overtime incurred through the labor of city employees, the value of the use of city equipment, and the cost of city materials used in the restoration project.
(G.O. No. 6966, § 1(Exh. A), 12-15-2025)
Ask a question about Springfield law
Corpus searches the Springfield sections it holds and shows the ones that match, with their citations. Free, no sign-in.