20.30.060 - Temporary roadway.
In all cases where excavations are made entirely across the public highway, a substantial roadway shall be maintained by the party making the excavation across the highway, until the excavation is refilled, and at all times be subject to the approval of the Director of Streets.
(1994 C., § 20.30.060; Ord. No. 68604, § 11, 3-16-2010.)
Ask a question about St. Louis law
Corpus searches the St. Louis sections it holds and shows the ones that match, with their citations. Free, no sign-in.