§ 207 — FINAL CONSTRUCTION PLANS "AS-BUILTS" AND SUBDIVIDERS RESPONSIBILITY

Comprehensive Development Regulations for the City of Flowood; partial · Flowood Development Regulations § 207

Corpus is an independent public-information project, not the official City of Flowood website. Stable reference: corpuslaw.us/code/924a7963-f625-44bc-bf9a-536b4c887ee2

SECTION 207 FINAL CONSTRUCTION PLANS "AS-BUILTS" AND SUBDIVIDERS RESPONSIBILITY

207.1 As-built Drawings

a. When construction is complete, substantially in accordance with the approved plans and specifications and complies with the provisions of these regulations, the engineer of record shall provide the city a set of as-built plans in PDF format.

b. As-built drawings shall include the following information:

1. Surveyed location and elevation of sanitary sewer manhole tops and inverts.

2. Surveyed location and elevation of sanitary sewer lift stations.

3. Surveyed location of sanitary sewer service lines.

4. Surveyed location of fire hydrants, gate valves and other water structures.

5. Surveyed location of water service lines.

6. Surveyed location and elevation of drainage structure (curb inlets, junction boxes, grate inlets, etc.) tops and inverts.

7. Pipe sizes and materials for water, sewer and storm drain lines.

8. Surveyed location and elevation of storm drain culvert inverts.

9. A dimension from each front lot corner to water and sewer service line location.

10. Easement lines, purpose, and owner of easement.

11. Water, sewer, and storm drain lines and structures in format dictated by the City for incorporation into the City’s GIS utility map.

12. Other information as deemed necessary by the City.

c. If the “as-built” plans include a detention basin and outlet structure, the “as-built” elevations must confirm that the pond and structure was installed in accordance with the approved plans. If, however, the “as-built” elevations do not agree with the original plans, the engineer shall be required to re-run the calculations in the “as-built” condition and submit them to the City for approval. Based on the findings of the re-submittal, the City may require the developer to correct the changes to agree with the plans.

d. The location of each water and/or sanitary wastewater service line shall be clearly and accurately shown on the “As-built” Drawings.

207.2 For a period of twelve (12) months after acceptance of the work by the City Engineer, the subdivider shall warranty all improvements and keep all filled trenches, pipes, manholes, structures, paved or unpaved surfaces, etc. which have been constructed by him in good condition making repairs to such defects in materials or workmanship which may develop or be discovered to the satisfaction of the City. If wastewater treatment plants and/or pumping stations are constructed, the subdivider shall guarantee materials and workmanship of these facilities for a period of twelve (12) months from the date of acceptance in accordance with standard warranty conditions of the equipment manufacturer.

207.3 In subdivisions, the location of water and sewer service mains shall be scored in the face of the curb of street by use of the symbol’s "W" for water and "Y" for sewer respectively.