SECTION 211 REQUIRED INSPECTIONS

211.1 Prior to starting construction and at the expense of the Subdivider/Owner, the Subdivider/Owner shall make arrangements to engage a licensed testing agency with MDOT approved testing laboratory to observe and perform testing on earthwork operations and perform materials testing all in accordance with Article III of these regulations for earthwork, concrete and pavement materials to ensure that the materials used and installation of such complies with these regulations and the project specifications. Records of such tests and inspections shall be provided to the Subdivider/Owner’s representative for keeping until such time as the City requests the reports.

211.2 Erosion and sediment control measures must be installed, inspected, and maintained in accordance with the City of Flowood’s permits, ordinances, these regulations and MDEQ’s requirements. The owner or his designee shall perform additional inspections as required by all governing state and federal agencies and shall be responsible for keeping their site in compliance. See Article VI of these regulations for more information on City requirements and procedures.

211.3 Additionally, the Subdivider/Owner shall employ a registered Professional Engineer to perform periodic inspections of the utility and street improvements as they are installed. This Engineer shall then certify to the City Engineer, City Public Works Director or other City Designee that each improvement has been construction in substantial accordance with the approved plat, construction plans and specifications, and requirements of this Ordinance.

211.4 Once all improvements have been completed in accordance with approved plans and specifications and notification of such by the Developer's Engineer of Record, the City Engineer, and or other City Designee shall make a Final Inspection of the improvements required by this Ordinance, and any other improvements to be accepted by the City. Unacceptable work, whether the result of poor workmanship, use of defective materials, damage through carelessness or any other cause found to exist prior to final acceptance of the work, shall be noted by the City and punch list shall be provided to the Subdivider/Owner for removal and replacement in an acceptable manner to the City’s satisfaction at no cost to the City. The City Designee, acting as the duly authorized representative of the City and subject to the rules and regulations contained herein, shall decide all questions that may arise as to quality or acceptability of materials furnished or work performed. Such decisions may be appealed to the Mayor and Board of Aldermen

and acceptance of each phase shall be binding upon the City subject to correction by the Developer and his contractor of any damage that might occur during subsequent work on other required improvements.

211.5 If the City Engineer, and or other City Designee has verified that the contracted improvements are complete and free from defect, then upon receipt of the Final Recording Plat, and any other statements and certificates and/or agreements, the Mayor and Board of Aldermen shall vote to accept the dedication of any portion of the required improvements, provided that all statements and agreements specified above have been received for that portion of the improvements.