SECTION 9.6: Major Subdivision Infrastructure Installation Process
Once Preliminary Plat Approval has been granted by City Council, the developer shall have construction drawings and other required submittals prepared and have improvements installed in accordance with this Section. 9.6.1 Pre-Submittal Meeting Prior to construction drawing and other submittal preparation, the developer and project engineer shall meet with City staff to discuss the construction requirements. The meeting may be scheduled by the developer by contacting the Planning Department. 9.6.2 Submittal of Required Construction Documents The developer shall submit three (3) complete full-size sets of construction drawings, specifications, and other required submittals of the proposed subdivision infrastructure improvements. The plans and specifications shall be prepared by a Professional Engineer licensed in the State of Mississippi. 9.6.3 Staff Review Staff will review the submittals and provide comments. Once all comments have been addressed, a minimum of three (3) sets of plans and specifications shall be stamped/signed by the project Professional Engineer registered in the State of Mississippi and submitted to the City for a permit. Such plans shall be approved prior to construction of any type beginning in the subdivision. The plans and specifications shall be approved; and all outside agency permits/approval shall be obtained prior to a permit being issued for construction. 9.6.4 Preconstruction Conference Once the developer has selected a contractor, a preconstruction conference shall be held. The developer or engineer shall coordinate the meeting and shall include City staff, the developer, the developer’s project engineer, and utility company representatives providing utilities to the site. Once the plans and specifications are approved; all outside agency permits/approvals have been obtained; the preconstruction conference has been held; the contractor has obtained the proper City licenses; and the proper fees have been paid in accordance with the City’s Comprehensive Fee Schedule; the construction permit may be issued by the Building Official. 9.6.5 Construction Once the construction permit has been obtained, the contractor may begin construction. The developer shall install all improvements in accordance with the approved construction drawings and this Ordinance. The developer/engineer shall ensure the City is adequately advised of any/all activities to construct the project and shall endeavor to maximize the City’s opportunity to observe the work. The developer/engineer shall ensure the City receives all the required construction paperwork in a timely manner during construction, including material submittals, equipment cut sheets, test reports, stormwater reports, etc. The engineer shall ensure any field changes are approved by the City and are documented in a timely manner on the “as-built” drawings. The developer’s engineer shall inspect the improvements as they are installed and certify that each improvement has been constructed in accordance with the approved plat, construction plans, and specifications and requirements of this Ordinance. 9.6.6 Construction Punchlist The Building Official shall be notified and be present for the punchlist walk-through. Once the punchlist is generated by the developer/engineer, the list shall be provided to the City for review. Staff shall review and provide any missing comments on the draft punchlist. Any comments shall be incorporated into the punchlist prior to providing to the contractor. 9.6.7 Final Inspection The City staff shall be notified when construction is complete, so a field inspection can be conducted of the completed work to verify that the required improvements have been properly constructed in conformity with the approved construction plans and specifications. Such a field inspection shall not relieve the developer of responsibility for any subsequent failure of the constructed improvements in whole or in part. The City will provide comments of any corrections needed. The comments will include any construction paperwork still required such as “as-builts”, product warranty information, owner’s manuals, outside agency final approvals, etc. The Developer’s engineer shall furnish the appropriate City staff person or consultant with a certificate stating that all work has been completed in conformity with the approved construction plans and specifications. 9.6.8 Warranty The developer shall warranty all improvements for two (2) years from the date of final plat approval by the City Council. A Guarantee of Improvements shall be posted for the warranty period.
Ask a question about Gautier law
Corpus searches the Gautier sections it holds and shows the ones that match, with their citations. Free, no sign-in.