Sec. 38.740.080. - Plan review procedures.

A. Conceptual review. 1. Conceptual review: a. Purpose. Conceptual review is an opportunity for an applicant to review the requirements, standards and procedures that apply to their development proposal. Major problems can be identified and solved during conceptual review before a formal application is made. The primary focus of conceptual review is to identify site specific challenges and/or constraints, critical path elements which will affect review process, or submittal requirements. b. Applicability. Conceptual review is required for development subject to 38.740.040 and not subject to 38.740.060. Conceptual review may be waived by the community development director for development proposals that would not derive substantial benefit from such review. c. Concept plan submittal. An applicant must submit the application materials required by the community development director as provided in the conceptual review checklist. d. Staff review and recommendation. Upon receipt of a concept plan, and after review of such plan by the DRC, the city must furnish the applicant with written comments regarding such plan, including appropriate recommendations to inform and assist the applicant prior to preparing the components of the formal development application. The city may invite other public or quasi-public agencies which may be impacted by the development to comment. These agencies may include gas and electric utilities, state agencies, ditch companies, railroads, cable television service providers, and other similar agencies. e. The applicant may as part of the concept review request a waiver from information required to be submitted with a plan review. The DRC may grant reasonable waivers from submittal of application materials required by these regulations where it is found that these regulations allow a waiver to be requested and granted. In order to be granted a waiver, the applicant must include with the submission of the concept plan a written statement describing the requested waiver and the reasons upon which the request is based. f. Formal application must address the comments provided with the conceptual review. A complete plan application must be submitted to the community development department within one calendar year of the date the concept comments are made available to the subdivider. B. Development application submittal. 1. Development application forms. All development applications must use forms and procedures established by the community development director. 2. Fees. All fees established in the adopted fee schedule must be paid prior to the review authority commencing review of the application. The city manager may waive, reduce, or pay for a required plan review fee. C. Review of applications. 1. The development review committee must review the application for completeness within 20 business days to determine if the application omits any of the submittal elements required by this chapter. If the application does not contain all of the required elements, a written explanation of what the application is missing must be provided to the property owner or their representative. The business days are met if the information is made available to the property owner or representative within the required time. A plan is reviewed against the criteria in effect on the date completeness is determined. a. The applicant shall provide the missing information within 30 business days of notification of incompleteness unless a longer period is agreed between city and applicant. The city may charge a fee for resubmittal of application materials. The city must review subsequent submissions of application material only for information found to be deficient during the original review of the application. b. A determination that an application is sufficient does not restrict the city from requesting additional information during the plan review process, nor does it ensure approval. c. If the applicant is nonresponsive to a request for additional information the termination provisions of 38.740.040 apply. 2. The DRC may grant reasonable waivers during concept review from submittal of application materials required by these regulations where it is found that these regulations allow a waiver to be requested and granted. In order to be granted a waiver the applicant must include with the submission of the preliminary plan a written statement describing the requested waiver and the reasons upon which the request is based. The review authority must consider each waiver at the time the plan is reviewed. 3. If in the opinion of the review authority the waived materials are necessary for proper review of the development, the materials must be provided before review is completed. 4. After accepting a sufficient application proposing development of a site, the review authority must make an initial determination: a. Whether the application, with or without variances or deviations, is in substantial compliance with all applicable regulations and the zoning map; and, b. Whether all impacts resulting from the proposed development have previously been analyzed and made available for public review during adoption, amendment, or update of the land use plan, zoning regulation, or zoning map. 5. If the review authority determines that the application is in substantial compliance, as defined in MCA 76-25-103, and impacts have previously been addressed, then public notice must be issued per 38.730 and opportunity to comment on the initial determination provided. 6. Unless public comment received on or before the last day of the comment period provided in subsection C.5 supports a determination that the proposed development fails to meet the requirements of subsection C.4, the review authority must issue written findings stating the results of the public comment and a final written decision approving, approving with conditions, or denying the application. The decision may be appealed as provided in 38.760.030. 7. If the review authority makes an initial determination that the criteria of subsection 4 are not met, or public comment received under subsection C.5 provides evidence that the proposed development, with or without variances or deviations from adopted standards, fails to meet either one or both of the requirements of subsection C.4, the review authority must: a. Request that the applicant collect any additional data and perform any additional analysis necessary to provide the planning administrator and the public with the opportunity to comment on and consider the lack of substantial compliance with the zoning regulations or zoning map and any new or significantly increased potential impacts not previously identified and considered in the adoption, amendment, or update of the land use plan, zoning regulations, or zoning map; b. Collect any additional data or perform additional analysis the planning administrator determines is necessary to provide the local government and the public with the opportunity to comment on and consider the lack of substantial compliance with the zoning regulations or zoning map and any new or significantly increased potential impacts not previously identified and considered in the adoption, amendment, or update of the land use plan, zoning regulations, or zoning map; and c. Provide public notice of the planning administrator's initial or revised initial determination in accordance with C.4 of and a 15-business day written comment period during which the public must have the opportunity to participate and comment on the data collected and analysis performed pursuant to subsections C.7.a and C.7.b. 8. Any additional data, analysis, comment, or consideration described in subsection C.7 must be limited to the lack of substantial compliance with the zoning regulations or map and any new or significantly increased impacts potentially resulting from the proposed development, to the extent the impact was not previously identified or considered in the adoption, or amendment, or update of the land use plan, or zoning regulations, or zoning map. 9. After the public comment period provided in subsection C.7 has ended, the planning administrator shall issue written findings stating the results of the public comment and a final written decision approving, approving with conditions, or denying the application, which may be appealed as provided in 38.760.030. D. Mitigation. The review authority may require the developer to design the development or take other actions to reasonably minimize potentially significant adverse impacts identified through the review required by this chapter. The review authority may not unreasonably restrict a landowner's ability to develop land, but it is recognized that in some instances the unmitigated impacts of a proposed development may be unacceptable and will preclude approval of the plan.

(Ord. No. 2025-12, § 4(Exh. A), 12-16-2025)