Sec. 60-89. - Final approval requirements and conditions.

(a) Final approval shall not be issued until the construction of the extension and/or modification to the stormwater conveyance and control system have meet all the applicable rules, regulations, statutes, and ordinances of the city, the State of North Carolina, and the United States of America. (b) The engineer shall certify that the installation and the construction of any extension and/or modification to the stormwater conveyance and control system shall meet all regulatory design standards and is in substantial compliance with the approved engineering plans and associated permits. (c) If the stormwater administrator should find that final approval should be denied, the denial shall be made in writing and shall contain each reason for the denial and the stormwater administrator's estimate of the general changes in the applicant's proposed activities or plan which will be required, in order that the applicant may obtain a final approval. Nothing in such estimate shall preclude or otherwise bar the stormwater administrator from denying final approval, which incorporates such changes, based upon changed circumstances or information not previously known by the stormwater administrator. (d) A properly executed certification, the "as-built" drawings, the "record" drawings, and the video assessment, as prescribed in section 60-85 of this article, shall be submitted to the stormwater administrator for review and shall be determined complete by the stormwater administrator before final approval is issued. (e) No construction, alteration, or expansion of the stormwater conveyance and control system shall be placed into final service until the applicant has fully complied with all applicable federal, state, and local regulations and standards and has obtained final approval from the stormwater administrator.

(Ord. No. 07-108, § 1, 12-13-2007)

Ask a question about Concord law

Corpus searches the Concord sections it holds and shows the ones that match, with their citations. Free, no sign-in.