§ 1310 — Assurance of improvements, performance guarantees, and inspection procedures

Code of Ordinances of the City of Rocky Mount, North Carolina (Codified through Ordinance No. O-2025-71, enacted November 10, 2025. (Supp. No. 90)) · Rocky Mount City Code § 1310

Corpus is an independent public-information project, not the official City of Rocky Mount website. Stable reference: corpuslaw.us/code/3088f77d-f643-4e08-ae1e-2b7c00c1102f

Sec. 1310. - Assurance of improvements, performance guarantees, and inspection procedures.

A. Improvement completion. Prior to approval of the final plat, the developer shall either complete the required improvements or post a sufficient performance guarantee to assure the successful completion of the required improvements. The procedures in each case are as follows: 1. Completion of improvements. Upon approval of as-built plans and when the developer has completed all improvements to the satisfaction of the director of public works, the director of public works shall issue to the developer certification that the improvements have been installed and have the final approval of the city subject to the one-year warranty period and posting of a warranty bond; or 2. Guarantee of completion of improvements. If the developer has not completed all of the required improvements, but the improvements have conditional approval by the director of public works, the developer shall file with the city a performance guarantee as provided in this subsection: (a) Type. The type of performance guarantee shall be at the election of the developer. The term "performance guarantee" shall mean any of the following forms of guarantee: (i) Surety bond issued by any surety company authorized to do business in North Carolina. (ii) Letter of credit issued by any financial institution licensed to do business in North Carolina. If the financial institution does not have an office within sixty (60) miles of the corporate limits of the City of Rocky Mount, the letter of credit shall provide a means by which it can be called without in person presentation. (iii) Other form of guarantee that provides equivalent security to a surety bond or letter of credit. (b) Duration. The duration of the performance guarantee shall initially be one (1) year, unless the developer determines that the scope of work for the required improvements necessities a longer duration. In the case of a bonded obligation, the completion date shall be set one (1) year from the date the bond is issued, unless the developer determines that the scope of work for the required improvements necessitates a longer duration. (c) Extension. A developer shall demonstrate reasonable, good-faith progress toward completion of the required improvements that are secured by the performance guarantee or any extension thereof. If the improvements are not completed to the specifications of the city, and the current performance guarantee is likely to expire prior to completion of the required improvements, the performance guarantee shall be extended, or a new performance guarantee shall be provided by the developer for an additional period; provided, however, that the period of the extension shall be approved by the city in its reasonable discretion, and provided further, in no event shall the extension be for a period longer than is reasonably necessary to complete the required improvements. If a new performance guarantee is issued, the amount shall be determined by the procedure provided in subdivision (e) of this subsection and shall include the total cost of all incomplete improvements. (d) Release. The performance guarantee shall be returned or released, as appropriate, in a timely manner upon the acknowledgement by the city that the improvements for which the performance guarantee is being required are complete. The city shall return letters of credit or escrowed funds upon completion of the required improvements to the specifications of the city, or upon acceptance of the required improvements, if the required improvements are subject to city acceptance. When required improvements that are secured by a bond are completed to the specifications of the city, or are accepted by the city, if subject to city acceptance, upon request by the developer, the city shall timely provide written acknowledgement that the required improvements have been completed. (e) Amount. The amount of the performance guarantee shall not exceed one hundred twenty-five (125) percent of the reasonably estimated cost to complete the improvements at the time the performance guarantee is issued. The city may determine the amount of the performance guarantee or use a cost estimate determined by the developer. The reasonably estimated cost of completion shall include one hundred (100) percent of the costs for labor and materials necessary for completion of the required improvements. Where applicable, the costs shall be based on unit pricing. The additional twenty-five (25) percent allowed under this subsection includes inflation and all costs of administration regardless of how such fees or charges are denominated. The amount of any extension of any performance guarantee shall be determined according to the procedures for determining the initial guarantee and shall not exceed one hundred twenty-five (125) percent of the reasonably estimated cost of completion of the remaining incomplete improvements still outstanding at the time the extension is obtained. (f) Timing. The performance guarantee shall be posted at or prior to the time the plat is recorded. (g) Legal responsibilities. No person shall have or may claim any rights under or to any performance guarantee provided pursuant to this subsection or in the proceeds of any such performance guarantee other than the following: (i) The local government to whom such performance guarantee is provided. (ii) The developer at whose request or for whose benefit such performance guarantee is given. (iii) The person or entity issuing or providing such performance guarantee at the request of or for the benefit of the developer. (h) Multiple guarantees. The developer shall have the option to post one (1) type of performance guarantee as provided for in subdivision (a) of this subsection in lieu of multiple bonds, letters of credit, or other equivalent security, for all development matters related to the same project requiring performance guarantees. Performance guarantees associated with erosion control and stormwater control measures are not subject to the provisions of this subsection 2. 3. Damage. If an approved phase of construction is damaged during subsequent phases of construction prior to a final approval of the completed construction for the entire development (subdivision), the developer shall be responsible for repair of the damage. All construction must be in acceptable operating condition for one (1) year prior to complete acceptance of maintenance and responsibility by the city. B. Inspection of construction. The inspection of all required improvements shall be required prior to the issuance of the certification of satisfactory installation and completion of said improvements. The developer shall arrange to have the necessary inspections conducted at times prearranged through the office of the director of public works. C. Modifications of design improvements. If at any time before or during the construction of the required improvements, it is demonstrated to the satisfaction of the director of public works that unforeseen conditions make it necessary to modify the location or design of such required improvements as were approved in the preliminary plat, the director of public works may authorize such modification, provided these modifications are within the spirit and intent of planning board approval and do not extend to waiver, or substantially alter the function of any improvements required by the planning board. D. Variances. The planning board may vary the requirements of chapter 13, minimum design and improvement requirements, when strict compliance with the standards would cause an unusual or unnecessary hardship on the developer due to the size of the tract to be subdivided, topography, condition or nature of adjoining areas, or existence of other unusual physical conditions. In granting variances from section 1302, the planning board may, where practical, require conditions that will secure the objectives and the requirement(s) varied. The issuance and justification for said variance shall be entered in the planning board's minutes. E. No permit to be issued. No permit shall be issued to any person, firm or corporation for the construction, reconstruction, alteration, or repair of any building, structure, or improvement upon real estate which has been subdivided in violation of this LDC. F. Actions against illegal transfer. The city, through its attorney or other official designated by the planning board, may bring an action for injunction of any illegal subdivision, transfer, conveyance, or sale of real estate and the court shall, upon appropriate findings, issue an injunction and order requiring the offending party to comply with the subdivision LDC. In addition to the foregoing, the provisions of this LDC may be enforced by any one (1), all, or a combination of the remedies authorized by N.C.G.S. § 160D-404. G. Metes and bounds description. The description by metes and bounds in the instrument of transfer or other document used to sell or transfer real estate shall not exempt the transaction from any penalty, action, or remedy provided for in this LDC.

(Ord. No. O-2021-2, §§ 2, 4, 1-11-21; Ord. No. O-2021-43, § 11, 6-14-21)