For AI agents: read the machine-readable documentation index at /llms.txt or the single-file full reference at /llms-full.txt.

§ 103-10 — Insurance and bonds required for demolition permits

Code of Ordinances of the City of Buffalo, New York (Code 2026-03-31: eCode360 publication current through the 2026-03-31 codification (imported 2026-11-12)) · Buffalo City Code § 103-10

Corpus is an independent public-information project, not the official City of Buffalo website. Stable reference: corpuslaw.us/code/08654e77-9012-43c6-a798-1f732c12a4d7

§ 103-10: Insurance and bonds required for demolition permits.

A. Prior to the issuance of any building permit for demolition, the applicant shall provide proof satisfactory to the Commissioner that a comprehensive liability policy exists which covers the demolition work. The Commissioner shall establish minimum limits of insurance. The Commissioner may require that the City be a named or additional insured. B. The Commissioner shall require applicants for a building permit for demolition to provide a performance bond to the City of Buffalo which shall insure completion of the demolition work to the standards established by the City. The value of the performance bond shall be equal to the full demolition cost. The Commissioner may accept a letter of credit or a certified check in substitution for the performance bond. The Commissioner may accept such bond, letter or check from an applicant to cover all work to be done by the contractor within a twelve-month period. The Commissioner may waive such bond, letter or check when there is no material need for such security. C. Before the permit is issued, the applicant shall file evidence that the owner or contractor is insured against public liability and property damage in connection with such work of demolition, in the sum of at least $2,000,000 per occurrence for public liability and $1,000,000 per occurrence for property damage. D. In addition to the foregoing evidence of insurance, the applicant shall, before any such permit is issued, file a bond with the City of Buffalo guaranteeing the City against any loss or damage by reason of such demolition work. The bond shall be in the amount of $100,000. E. In lieu of the bond required in Subsection D above, the applicant may file with the City a policy of public liability and property damage insurance, in which policy the City of Buffalo is named as an assured. Said policy of insurance shall protect the City against any loss or damage by reason of the work of demolition in the sum of at least $2,000,000 per occurrence for public liability and $1,000,000 per occurrence for damage to property. The aforesaid provisions regarding bond or insurance may be increased on very large or complex projects where the risk is felt to be greater by the Commissioner. F. No bond or liability policy shall be required to be filed with the City before the permit is issued to tear down, demolish, wreck or dismantle, in whole or in part, any building not more than 1 1/2 stories in height and with no basement or cellar, provided that the work is done by the individual owner of the building without assistance, and provided that the building is not located within 10 feet of any street line. G. Where the owner of a building of not more than 2 1/2 stories in height, or his agent, privately engages any person, firm or corporation to demolish, dismantle, wreck or tear down any building in whole or in part or to assist therein, the person, firm or corporation shall, prior to the issuance of a permit therefor, furnish to the Commissioner of Inspections and Licenses a copy of the contract or agreement therefor, which contract shall clearly state the work to be performed, the total cost thereof to the owner, the time of commencement of the work and the date of completion thereof. The contract shall also contain a clause providing for the rescission of the contract, at the option of the owner, within three days of receipt of an executed copy of the contract by the owner. No permit shall be issued to a contractor in the absence of a written executed agreement between the owner and the contractor. H. The applicant, shall before a permit is issued, provide a bond equal to the full demolition cost, providing that the demolition work shall be completed within 60 days (unless additional time is given by the Commissioner in writing) from the granting of the permit; provided, however, that this bond shall not be required for demolition work ordered by the City of Buffalo unless the specifications upon which bids are taken for such work require the same. Said bond shall be further conditioned for the faithful and complete performance of the contract for the work in strict compliance with the contract. All other provisions of the Code of the City of Buffalo relating to demolitions, including the provisions for various forms of insurance, shall also be applicable in the case of an owner of a building of not more than 2 1/2 stories in height who privately engages any person, firm or corporation to demolish, dismantle, wreck or tear down a building or any part thereof or to assist in its demolition, dismantling, wrecking or tearing down.

[Amended 7-20-2004 , effective 8-2-2004 ]

Ask a question about Buffalo law

Corpus searches the Buffalo sections it holds and shows the ones that match, with their citations. Free, no sign-in.