§ 2.11.60 — Variances

Municipal Code of the City of Corvallis, Oregon (Codified through Ordinance No. 2026-31, enacted October 19, 2026. (Supp. No. 70, Update 2)) · Corvallis Land Development Code § 2.11.60

Corpus is an independent public-information project, not the official City of Corvallis website. Stable reference: corpuslaw.us/code/ef76da89-ffd5-4585-8a8f-c91a466d8316

Section 2.11.60 - Variances.

An application filed for a Floodplain Development Permit Variance must comply with the following: 2.11.60.01 Limited Scope of Variance Applications. a. Variances are limited to the following: 1. Altering the required elevation standard for new construction and Substantial Improvements on a lot less than or equal to one-half acre, provided the lot is contiguous to and surrounded by lots with existing structures constructed below the Base Flood Elevation; 2. Allowing a Water Dependent use, provided structures or other Development are protected by methods that minimize flood damages during the Base Flood and create no additional threats to public safety; 3. Reconstructing, rehabilitating, or restoring a Designated Historic Resource upon a determination that the proposed restoration, rehabilitation, or restoration will not preclude the structure's continued designation as a Designated Historic Resource and the Variance is the minimum necessary to preserve the historic character and design of the structure; or 4. Allowing a lesser degree of floodproofing than watertight or dry-floodproofing for nonresidential buildings in very limited circumstances, where it can be determined that such action will have low damage potential and otherwise comply with Building Codes. b. Variance requests that exceed the limited scope described above in "a," above, must be made through the Planned Development process in Chapter 2.5 - Planned Development. 2.11.60.02 Variance Application Requirements. When the Floodplain Administrator or designee deems any requirement below unnecessary for proper evaluation of a proposed application, it may be waived. The applicant must include the following in a Floodplain Development Permit Variance Application: a. The items listed above in Section 2.11.50.01; b. Narrative explaining the basis for the Variance request and how the request still meets the purposes in Sections 2.11.20 and 4.5.10; c. Other narrative and technical information sufficient to demonstrate compliance with the review criteria in Section 2.11.60.06. The applicant must also provide narrative and technical information sufficient to demonstrate compliance with the review criteria in Section 2.11.50.04 which can still be met, despite the Floodplain Development Permit Variance request; and d. Required fees as described in LDC § 1.2.100.01. 2.11.60.03 Acceptance of Variance Application. An application for a Floodplain Development Permit Variance will be accepted and reviewed in accordance with the procedures in Section 2.12.30.02.b, except that public notice distance will be in accordance with Section 2.11.60.04, below. 2.11.60.04 Public Notice for a Variance Application. The public notice for a Floodplain Development Permit Variance will be issued in accordance with the provisions in Section 2.0.50.04, except that the public notice distance is 300 ft., as required for the land use applications in Section 2.0.50.04.c.2. 2.11.60.05 Staff Evaluation. The Floodplain Administrator or designee will prepare a report that evaluates whether or not the proposal qualifies as a Floodplain Development Permit Variance per Section 2.11.60.01, includes the required application materials per Section 2.11.60.02, meets the purposes in Sections 2.11.20 and 4.5.10, and complies with the review criteria in Section 2.11.60.06. The Floodplain Administrator or designee will also evaluate the proposed Floodplain Development Permit Variance with respect to the review criteria in Section 2.11.50.04, to see how many of the criteria can still be met. The report will include a recommendation for approval or denial and, if needed, a list of conditions for the Planning Commission to consider if an approval is granted. 2.11.60.06 Review Criteria for a Variance Application. In reviewing requests for the approval of a Floodplain Development Permit Variance, the Planning Commission will consider the purposes of this Chapter, the purposes in Section 4.5.10, the Variance thresholds contained in Section 2.11.60.01, the base Floodplain Development Permit review criteria in Section 2.11.50.04, standards specified in other sections of this chapter and Chapter 4.5 - Floodplain Provisions, all technical evaluations, and the criteria in "a," through "d," below. All of the criteria in "a," through "d," below, must be met. In addition, all of the review criteria in Section 2.11.50.04 must be met, with the exception of specific aspects of the criteria that cannot be met because of the nature of the Floodplain Development Permit Variance request. It is the applicant's burden to show that the Variance is warranted and meets said criteria. a. Variances will not be issued within a designated Floodway if any increase in flood levels during the Base Flood discharge would result. [4] b. Variances will only be issued upon a determination that the Variance is the minimum necessary, considering the flood hazard, to afford relief. c. Variances will only be issued upon a: 1. Showing of good and sufficient cause; 2. Determination that failure to grant the Variance would result in exceptional hardship to the applicant; 3. Determination that the granting of the Variance will not result in increased flood heights, additional threats to public safety, extraordinary public expense, or creation of nuisances; and 4. Determination that the granting of the Variance will not cause fraud on or victimization of the public, or conflict with existing local laws or ordinances. d. Variances will consider the following additional factors: 1. The danger that materials may be swept onto other lands to the injury of others as a result of approving the Variance request; 2. The potential to endanger life and property due to flooding or erosion damage caused by approval of the Variance request; 3. The susceptibility of the proposed facility and its contents to flood damage, and the effect of such damage on the individual owner and adjacent properties; 4. The importance of the services provided by the proposed facility to the community; 5. The necessity to the facility of a waterfront location, where applicable; 6. The availability and viability of alternate locations for the proposed use that are not subject to flooding or erosion damage; 7. The compatibility of the proposed use with existing and anticipated Development. This criterion will be considered satisfied if the proposed application meets the review criteria in Section 2.11.50.04.e; 8. The relationship of the proposed use to the Floodplain management program for that area; 9. The safety of access to the property in times of flood for ordinary and emergency vehicles; 10. The expected heights, velocity, duration, rate of rise, and sediment transport of the flood waters, and the effects of wave action, if applicable, expected at the site; and 11. The costs of providing governmental services during and after flood conditions, including maintenance and repair of public utilities and facilities such as sewer, gas, electrical, and water systems, and streets and bridges. 2.11.60.07 Action on Variance Application. The Planning Commission will conduct a quasi-judicial public hearing in accordance with Chapter 2.0 - Public Involvement. Following the close of the public hearing, the Commission will approve, conditionally approve, or deny the Floodplain Development Permit Variance. The Commission's decision will include findings that specify how the application has or has not complied with the review criteria in Section 2.11.60.06. The Commission's decision will also include findings that specify the extent to which the application has or has not complied with the original Floodplain Development Permit review criteria in Section 2.11.50.04. 2.11.60.08 Notice of Disposition. The Floodplain Administrator or designee will provide the applicant with a Notice of Disposition in accordance with Chapter 2.0 - Public Involvement that includes a written statement of the Planning Commission's decision, a reference to findings leading to it, any Conditions of Approval, and the appeal period deadline. If a Variance is granted to allow the construction of a building below the Base Flood level, the Notice of Disposition will include the following statements directed to the property owner and applicant: • the permitted building will have its Lowest Floor below the Base Flood Elevation or flood depth; • such construction below the Base Flood Elevation increases risks to life and property; • the cost of flood insurance likely will be commensurate with the increased flood damage risk; and • flood insurance rate premiums are determined by federal statute according to actuarial risk and will not be modified by the granting of a variance The Floodplain Administrator or designee will mail or email a Notice of Disposition to persons who presented oral or written testimony at the public hearing. 2.11.60.09 Permanent Retention of Variance Applications. The Floodplain Administrator or designee will maintain a permanent record of all Floodplain Development Permit Variances, and report any Variances to the Federal Emergency Management Agency upon request. 2.11.60.10 Appeals. The decision of the Planning Commission may be appealed in accordance with Chapter 2.19 - Appeals. 2.11.60.11 Effective Date. Unless an appeal has been filed, the decision of the hearing authority is effective 12 days after the Notice of Disposition is signed. 2.11.60.12 Effective Period of Approval. a. A Floodplain Development Permit Variance expires 180 days after issuance unless: 1. Start of Construction for the permitted activity has occurred and thereafter is pursued to completion; 2. An extension consistent with Building Permit extension procedures is granted by the Floodplain Administrator or designee, in cases where Start of Construction has not yet occurred. However, the granting of such extension will also require the Floodplain Administrator or designee to review the Floodplain Development Permit Variance activity(ies) relative to the applicable Code requirements to ensure that the scope of the Variance activities has not deviated further from Code provisions as a result of any subsequent Land Development Code Text Amendment(s). If the Floodplain Administrator or designee finds that the Floodplain Development Permit Variance has not deviated further from the applicable Code requirements, then the extension may be granted by the Floodplain Administrator or designee. If the Floodplain Administrator or designee finds that the Floodplain Development Permit Variance does indeed vary further from applicable Code requirements, then the Floodplain Administrator or designee will deny the extension request. b. Commencement of work includes Start of Construction, when the permitted work requires a Building Permit.

(Ord. No. 2012-17, eff. 12-13-2012; Ord. No. 2018-01, eff. 1-26-2018; Ord. No. 2021-06, eff. 5-25-2021; Ord. No. 2024-26, § 11(Exh. A), eff. 1-1-2025; Ord. No. 2025-31, §§ 2, 7(Exh. A), 7-21-2025)

Ask a question about Corvallis law

Corpus searches the Corvallis sections it holds and shows the ones that match, with their citations. Free, no sign-in.