§ 538-14: Erosion and sediment control during regulated earth disturbance activities.
A. No regulated earth disturbance activities within the City shall commence until approval by the City of an erosion and sediment control plan for construction activities. Written approval by DEP or a delegated County Conservation District shall satisfy this requirement. (1) It is the intent of this section of this chapter to require that property erosion control be maintained on all land regardless of the area of land intentionally disturbed (if any) and regardless of the status of any construction on the land. Should the City Engineer, and/or an LCCD representative, determine that erosion control on any area of land is deficient and impacting or threatening to impact on off-site land, either directly or indirectly (such as through the creation of sinkholes that may travel off-site), the City Engineer will require that corrective action be taken in an expeditious manner. This corrective action shall be completed as soon as possible, but no later than 10 days from the date of notification of the deficiency. (2) Should the City Engineer determine that erosion control is deficient during construction, the City Engineer may pull all construction permits acquired from the City and except for corrective erosion control work-stop the job until, in the opinion of the City Engineer, adequate correction of erosion control deficiencies has been made. B. An erosion and sediment control plan is required by DEP regulations for any earth disturbance activity of 5,000 square feet or more under 25 Pa. Code § 102.4(b). C. A DEP NPDES stormwater discharges associated with construction activities permit is required for regulated earth disturbance activities under 25 Pa. Code Chapter 92a. D. Evidence of any necessary permit(s) for regulated earth disturbance activities from the appropriate DEP regional office or County Conservation District must be provided to the City before the commencement of an earth disturbance activity. E. A copy of the erosion and sediment control plan and any permit, as required by DEP regulations, shall be available at the project site at all times.
[Amended at time of adoption of Code (see Ch. 1, General Provisions, Art. I)]