§ 8.7 — Construction, Guarantee of Performance, and Acceptance of Public Infrastructure

Code of Ordinances of the City of College Station, Texas (Supp. No. 10 Update 2: codified through Ordinance No. 2026-4726, adopted October 22, 2026) · College Station Land Development Ordinances, App. A, § 8.7

Corpus is an independent public-information project, not the official City of College Station website. Stable reference: corpuslaw.us/code/7d32fe89-a84f-493a-b6fe-710e6b29cd13

Sec. 8.7. - Construction, Guarantee of Performance, and Acceptance of Public Infrastructure.

Construction of private improvements is prohibited until the requirements for constructing or guaranteeing the construction of public infrastructure are met as set forth herein. A. Construction. 1. Development Permit. Upon approval of the construction documents by the City Engineer and issuance of a development permit, the subdivider may proceed with the construction of public infrastructure. Neither the developer nor the contractor nor the subcontractor shall make a connection to or tap into the City water distribution system, electric system, or sanitary sewer system until this requirement is met. The developer shall furnish all necessary materials to make the final tap or connection. 2. Letter of Completion and Acceptance. When the developer constructs the required public infrastructure, all such construction shall be inspected while in progress, by the City, and must be approved upon completion by the City Engineer. A letter of completion will be issued by the City Engineer when: a. The construction conforms to the approved plans and the Bryan/College Station Unified Design Guidelines and the Bryan/College Station Unified Technical Specifications and all applicable City, state, and federal regulations; b. The developer provides construction red-lined record drawings signed by the contractor acceptable to the City Engineer that contain the following attestation: "I, ___________ General Contractor for ___________ development, certify that the improvements shown on this sheet were actually built, and that said improvements are shown substantially hereon. I hereby certify that, to the best of my knowledge, the materials of construction and sizes of manufactured items, if any are stated correctly hereon." ___________ General Contractor c. The developer and their agent/contractor, if applicable, sign the letter of completion which furnishes the City a written guarantee that all workmanship and materials shall be free of defects for one (1) year from the date of acceptance by the City Engineer; and d. Off-site easements relating to the public infrastructure have been recorded or are presented to the City and are acceptable to be recorded. 3. Upon completion by the developer and formal acceptance by the City of the public infrastructure required to be completed by the developer, they shall become the property of the City of College Station. B. Guarantee of Performance. 1. In lieu of the obligation to construct public infrastructure as set forth above, the developer may elect to file security guaranteeing the construction of the same to obtain final plat approval and to commerce construction of private improvements. This may be accomplished in one (1) of the following two (2) ways: a. Performance Bond. The developer may file with the City Engineer a bond executed by a surety company holding a license to do business in the State of Texas, in an amount acceptable to the City Engineer of the City of College Station, and a form approved by the City Attorney. The developer shall state in writing a timeframe acceptable to the City by when such public improvements will be complete; or b. Letter of Credit. The developer has filed with the City Engineer an irrevocable letter of credit, in a form approved by the City, signed by a principal officer of a local bank, local savings and loan association, or other financial institution, acceptable to the City, agreeing to pay to the City of College Station, on demand, a stipulated sum of money to apply to the estimated cost of installation of all improvements for which the developer is responsible under this Section. The guaranteed payment sum shall be the estimated costs and scheduling as prepared by the developer's engineer and approved by the City Engineer. The letter shall state the name of the subdivision and shall list the improvements which the developer is required to provide. 2. If one (1) of the two (2) types of security is filed by the developer and accepted by the City as described above, the City Engineer shall inspect and approve the construction of public improvements in accordance with the requirements of this UDO when the same occurs. If the developer fails to properly construct some or all required public improvements, the City Attorney shall, on the direction of the City Council, proceed to enforce the guarantees provided in this Section. 3. The City Engineer may extend the period by when completion of public improvements is to occur regardless of periods that may be iterated elsewhere in this UDO. No such extension shall be granted unless security, as provided herein, has been provided by the developer covering the extended period and provided that such extension does not jeopardize the general public health, safety, and welfare.

(Ord. No. 2023-4453, Pt. 1(Exh. A), 8-10-2023; Ord. No. 2024-4496, Pt. 1(Exh. H), 1-25-2024)