SECTION 5.03 — TIMING OF PUBLIC IMPROVEMENTS

Code of Ordinances, City of Frisco, Texas (Frisco City Code, Home Rule Charter and Code Appendix current through Ordinance 2026-10-64 adopted October 20, 2026 (eCode360 publication FR6313, scraped 2026-11-18)) · Frisco City Code § SECTION 5.03

Corpus is an independent public-information project, not the official City of Frisco website. Stable reference: corpuslaw.us/code/531e51cc-f6bc-4f9a-b026-f7b23e2dab65

SECTION 5.03: TIMING OF PUBLIC IMPROVEMENTS.

(a) Completion Prior to Final Plat Approval & Recordation. Completion of all required public improvements, in accordance with the approved Preliminary Plat and the approved Construction Plans, shall occur prior to Final Plat approval and recordation. A Final Plat shall not be accepted for filing, nor shall it be considered for approval, prior to completion of such improvements except as provided in subsection (b). (b) Completion After Final Plat Approval & Recordation. The Director of Engineering Services, upon written request by the applicant, may allow construction of public improvements after Final Plat approval and recordation. Such postponement shall be conditioned on execution of an Improvement Agreement and provision of security, in accordance with Section 5.04. It shall be at the Director's discretion to determine whether postponing construction of public improvements until after Final Plat approval and recordation is appropriate, and therefore, whether financial guarantee is acceptable through an Improvement Agreement. (c) Deferral of Obligation. The Director of Engineering Services may defer the developer's obligation to dedicate rights-of-way for, or to construct, public improvements to serve a new development upon execution of an Improvement Agreement and upon provision of adequate security (see Section 5.04). (d) Phased Development. If the development is being platted and constructed in phases, improvements shall be completed as platted areas are approved and phases are constructed. Also refer to Section 4.02(i) for details regarding phased development and Preliminary Plat validity. (e) Easements for Utility Providers. The applicant is responsible for contacting all utility providers prior to beginning construction, and for securing all necessary easements for same prior to Final Plat approval and recordation. The applicant's engineer shall provide the Director of Engineering Services with written certification that all necessary easements are secured for the various utility providers, and such easements shall be shown on the Final Plat with the recording information for each. (f) Off-Site Easements. All necessary off-site easements required for installation of required off-site public improvements to serve the development shall be acquired by the applicant prior to the Pre-Construction Meeting (see Section 5.02), or prior to approval and recordation of the Final Plat, whichever occurs first. Off-site easements shall be conveyed and recorded at the County by an instrument approved by the City. If the property on which the off-site easement is required has been platted, a replat is required to dedicate the easement.

( Ordinance 19-08-70 adopted 8/20/2019 )