§ 105-44: Variance procedures.
(a) Following recommendation from the Floodplain Administrator and City Engineer or appointed Professional Engineer, the Appeal Board, as established by the community, shall hear and render judgment on requests for variances from the requirements of this chapter. The issuance of a variance pursuant to this chapter is for floodplain management purposes only. (b) The Appeal Board shall hear and render judgment on an appeal only when it is alleged there is an error in any requirement, decision, or determination made by the Floodplain Administrator in the enforcement or administration of this chapter. The Appeal Board, after a public hearing and examining the applicant's hardships, shall approve or disapprove a request for variance. (c) Any person or persons aggrieved by the decision of the Appeal Board may appeal such decision in the courts of competent jurisdiction. (d) The Floodplain Administrator shall maintain a record of all actions involving an appeal and shall report variances to the Federal Emergency Management Agency upon request. (e) Variances may be issued for the reconstruction, rehabilitation or restoration of structures listed on the National Register of Historic Places or the State Inventory of Historic Places, without regard to the procedures set forth in the remainder of this chapter. Variances may be issued for the repair or rehabilitation of historic structures upon a determination that the proposed repair or rehabilitation will not preclude the structure's continued designation as a historic structure and the variance is the minimum necessary to preserve the historic character and design of the structure. (f) Variances may be issued for new construction and substantial improvements to be erected on a lot of one-half acre or less in size contiguous to and surrounded by lots with existing structures constructed below the base flood level, providing the relevant factors in section 105-43(b) of this article have been fully considered. As the lot size increases beyond the one-half acre, the technical justification required for issuing the variance increases. (g) Upon consideration of the factors noted above and the intent of this chapter, the Appeal Board may attach such conditions to the granting of variances as it deems necessary to further the purpose and objectives of this chapter (section 105-3). (h) Variances shall not be issued within any designated floodway if any increase in flood levels during the base flood discharge would result. (i) Prerequisites for granting variances: (1) Variances shall only be issued upon a determination that the variance is the minimum necessary, considering the flood hazard, to afford relief. (2) Variances shall only be issued upon: a. Showing a good and sufficient cause; b. A determination that failure to grant the variance would result in exceptional hardship to the applicant due to the physical characteristics of the land that render the lot undevelopable; inconvenience and/or increased costs to satisfy the requirements do not constitute hardship, and c. A determination that the granting of a variance will not result in increased flood heights, additional threats to public safety, extraordinary public expense, create nuisances, cause fraud on or victimization of the public, or conflict with existing local laws or ordinances. (3) Any applicant to whom a variance is granted shall be given written notice that the structure will be permitted to be built with the lowest floor elevation below the base flood elevation, and that the cost of flood insurance will be commensurate with the increased risk resulting from the reduced lowest floor elevation. (j) Variances may be issued by a community for new construction and substantial improvements and for other development necessary for the conduct of a functionally dependent use provided that: (1) The criteria outlined in section 105-44(a) through (j) are met and (2) The structure or other development is protected by methods that minimize flood damages during the base flood and create no additional threats to public safety. (k) Enforcement of conditions and violation. Any variance granted under this chapter shall be subject to the conditions and safeguards established at the time of approval. Failure to comply with such conditions, or misuse of the variance, shall be considered a violation of this chapter and may result in revocation of the variance and any other lawful remedy as determined appropriate by the City.
( Ordinance 2026-38 adopted 8/19/2026 )
Ask a question about Harlingen law
Corpus searches the Harlingen sections it holds and shows the ones that match, with their citations. Free, no sign-in.