Sec. 110-266. - Permit application.
(a) Significant industrial users required to obtain an industrial wastewater discharge permit shall complete and file with the environmental officer an application upon a form provided by the city. A permit fee shall accompany the application. In support of the application, the significant industrial user shall submit the following information: (1) Identifying information. The user shall submit the name and address of the facility, including the name of the operators and owners. (2) Permits. The user shall submit a list of any environmental control permits held by or for the facility. (3) Description of operations. The user shall submit a brief description of the nature, average rate of production, and the standard industrial classification of the operations carried out by such industrial user. This description should include a schematic process diagram which indicates points of discharge to the POTW from the regulated processes. (4) Flow measurement. a. The user shall submit information showing the measured average daily and maximum daily flow, in gallons per day, to the POTW from each of the following: 1. Regulated process streams; and 2. Other streams as necessary to allow use of the combined wastestream formula of 40 CFR 403.6(e). b. The control authority may allow for verifiable estimates of these flows where justified by cost or feasibility considerations. (5) Wastewater data. Wastewater constituents and characteristics, including, but not limited to, those mentioned in this division and any federal, state or local standards. Sampling and analysis shall be performed in accordance with procedures established by the EPA pursuant to section 304(g) of the act; in 40 CFR 136, as amended; and in 40 CFR 403.12(b)(5), as amended. (6) Certification. A statement, reviewed by an authorized representative of the industrial user, as defined in section 110-268, and certified by a qualified professional, indicating whether pretreatment standards are being met on a consistent basis, and, if not, whether additional operation and maintenance (O&M) and/or additional pretreatment is required for the industrial user to meet the pretreatment standards and requirements. (7) Compliance schedule. a. If additional pretreatment and/or O&M will be required to meet the pretreatment standards, the shortest schedule by which the industrial user will provide such additional pretreatment and/or O&M. The completion date in this schedule shall not be later than the compliance date established for the applicable pretreatment standard. b. The following conditions shall apply to the schedule required by this subsection: 1. The schedule shall contain increments of progress in the form of dates for the commencement and completion of major events leading to the construction and operation of additional pretreatment required for the industrial user to meet the applicable pretreatment standards (e.g., hiring an engineer, completing plans, executing contract for major components, commencing construction, completing construction, etc.); and 2. No increment referred to in subsection (a)(7)a of this section shall exceed nine months. c. Not later than 14 days following each date in the schedule and the final date for compliance, the industrial user shall submit a progress report to the control authority including, at a minimum, whether or not it complied with the increment of progress to be met on such date and, if not, the date on which it expects to comply with this increment of progress, the reason for delay, and the steps being taken by the industrial user to return the construction to the schedule established. In no event shall more than nine months elapse between such progress reports to the control authority. (8) Other information. Any other information as deemed necessary by the city to evaluate the permit application. (b) The environmental officer shall issue a permit if he determines that pretreatment facilities are adequate for efficient treatment and that discharged wastes will comply with the requirements of sections 110-255 and 110-256 and state or federal pretreatment standards, if applicable.
(Code 1982, § 31-128; Ord. No. 92-07-19, § 13, 7-7-1992)
Ask a question about McKinney law
Corpus searches the McKinney sections it holds and shows the ones that match, with their citations. Free, no sign-in.