§ 19-14 — Contracts negotiated between developer and contractor without formal bids
Code of Ordinances of the City of Tyler, Texas (September 2026: including amendments through September 9, 2026) · Tyler City Code § 19-14
Corpus is an independent public-information project, not the official City of Tyler website. Stable reference: corpuslaw.us/code/fa72f2e5-c3cf-41c5-8f74-4a0040615e69
Sec. 19-14. Contracts negotiated between developer and contractor without formal bids.
1. The developer shall award the contracts for construction of water or sewer facilities, including off-site mains and service connections. 2. The developer shall pay all of the cost of all water or sewer facilities, including off-site mains and service connections without participation or refund by the City. 3. Design, development of construction plans, specifications and contract documents, and construction staking for the water or sewer facilities to be constructed shall be performed by a registered professional engineer in Texas and shall conform to the same design guidelines and criteria which governs utilities construction contracts let by the City, including providing to the City as-built plans following completion of construction. The developer shall provide to the Director six (6) sets of construction plans, specifications and contract documents prior to issuance of project work order. The developer shall follow and adhere to all applicable provisions and specifications of the Tyler Unified Development Code in Chapter 10 of the City of Tyler Code of Ordinances. 4. Before a developer may award a contract to any prospective contractor for construction of water or sewer facilities, it must be established that the contractor has been approved by the Director for work on City water and sewer systems. 5. The issuance of order to commence work shall be approved by the Director and all water and sewer construction shall be subject to inspection and control at any and all times by the department's inspection personnel. In no case may any water or sewer facility be installed unless the responsible City inspector is present and gives consent to proceed. Laboratory tests of materials being used shall be made as may be required by the City as necessary to assure compliance with governmental specifications.. 6. Choices for Developers to Provide Assurance. Prior to commencing work, the developer shall have plans approved by the City. In addition, prior to final acceptance of the work by the City, the developer shall meet the requirements set forth in either subsection a. OR subsection b below. a. Choice 1.-If developer chooses to furnish bonds, the following requirement shall be met: (i.) Submission of a one hundred percent (100%) payment bond in the name of the City, covering construction of the facility to be built; and (ii.) Submission of a guarantee or maintenance bond for one hundred percent (100%) of the cost of improvements in the name of the City covering the facility against defects in materials and/or workmanship for a period of one year after completion and acceptance of the facility by the Director. (iii.) All required improvements shall be completed to the City of Tyler standards and specifications; and (iv.) A final inspection of completed improvements shall be performed by the City Engineer or authorized representative, and work must be approved and/or accepted by the City of Tyler. The developer shall maintain all improvements until improvements have been accepted by the City of Tyler; and (v.) Complete record drawings of required improvements have been submitted to and approved by the City Engineer: and b. Choice 2.- If developer does not choose to furnish a payment bond per subsection a., then before a plat is filed with the county clerk, the following requirements shall be met: (i.) All required improvements shall be completed to the City of Tyler standards and specifications; and (ii.) A final inspection of completed improvements shall be performed by the City Engineer or authorized representative, and work must be approved and/or accepted by the City of Tyler. The developer shall maintain all improvements until improvements have been accepted by the City of Tyler; and (iii.) The general contractor shall submit an Affidavit of All Bills Paid to the City Engineer certifying that all construction bills have been paid, and materials and workmanship are guaranteed for one year; and (iv.) Complete record drawings of required improvements have been submitted to and approved by the City Engineer. (v.) Submission of a guarantee or maintenance bond for one hundred percent (100%) of the cost of improvements in the name of the City covering the facility against defects in materials and/or workmanship for a period of one year after completion and acceptance of the facility by the Director. 7. Final payments to contractors shall be approved by the Director prior to payment and only after the improvements have had at least preliminary acceptance by City. This approval pertains to the satisfactory completion of the work for which payment is made and does not constitute approval of the quantities on which the payment is based. 8. Prior to the award of any construction contract, the developer shall convey easements acceptable to the Director covering all land which will be occupied by the proposed lines and water or sewer facilities. 9. Connections of buildings to service connections are prohibited until the water or sewer facilities to which they connect have been declared available for service and had preliminary acceptance by the Director. 10. Title and ownership of all sanitary sewers or water mains constructed under the terms of this option, exclusive of service connections, shall be vested in the City upon final acceptance by City. 11. Water or sewer facilities constructed under this option will not receive final acceptance by the City until all developmental improvements are completed and accepted by City. Maintenance and reconstruction of the facilities during the period between preliminary and final acceptance will be the responsibility of the developer. (a) No construction shall begin under the terms of this section until the developer agrees to all requirements of this section. (b) Water or sewer extension projects in which the City pays a portion of the cost may not be constructed pursuant to the rules provided by this Section. (0rd. 0-97-27, 5/28/97) (Ord. No. 0-99-80, 10/20/99) (Ord. No. 2009-7, 2/11/09) (Ord. No. O-2019-63, 08/14/2019)
Ask a question about Tyler law
Corpus searches the Tyler sections it holds and shows the ones that match, with their citations. Free, no sign-in.