§ 9-7-3 — SPECIAL CONDITIONS
City Code of Lehi City, Utah (2026 S-12) · Lehi City Code § 9-7-3
Corpus is an independent public-information project, not the official City of Lehi website. Stable reference: corpuslaw.us/code/6ce0be95-2798-4fc5-ac16-876dc25c3f1e
9-7-3: SPECIAL CONDITIONS:
A. The customer shall pay for the net energy used in accordance with the following formula: 1. The customer shall pay for all electric energy supplied by the city to the customer in any billing period in excess of the amount of electric energy produced by the customer on the premises which is fed back into the city's electric distribution system during that same billing period. 2. The customer shall receive a credit for all electric energy produced by the customer on the premises which is fed back into the city's electric distribution system during a billing period in excess of the amount of electric energy supplied by the city during that billing period, with such credit applied to the customer's future electric bills, except that any electric energy credit balance remaining in favor of the customer at the time of their March billing each year shall be zeroed out with no further liability to the city and no credit to the customer for said balance. 3. In the event the customer terminates service under this electric service schedule, any electric energy credit balance in favor of the customer under the provisions of subsection A2 of this section shall be forfeited. The city will not make cash payments to customers based on their participation in the net metering program for energy produced by the customer which is fed into the city's electric distribution system. B. The price for electric energy provided to, or credited to, a customer participating in the net metering program shall be the price charged by the city under the provisions of the electric service schedule for which the customer receives service, absent this electric net metering program. C. The net metering program billing adjustment only applies to charges for energy. Participating customers are subject to all other charges, rates, terms and conditions of the electric service schedule under which the customer receives service, except as expressly altered by this electric service net metering program. D. The city power will be the owner of the renewable attributes of the electricity that is generated, to include any and all credits, RECs, S-RECs, certificates, benefits, environmental attributes, emissions reductions, offsets and allowances, however entitled, attributable to the generation of electricity from the customer owned renewable generation and its displacement of conventional energy generation. E. The customer shall provide, at the customer's own expense, all equipment necessary to meet applicable safety, power quality, and interconnection requirements established by the national electrical code (NEC), the Institute Of Electrical And Electronics Engineers (IEEE), Underwriters Laboratories (UL), and any applicable local and state agencies, including any equipment deemed necessary by the city's power department expressly to accommodate the customer's request to qualify for this electric service net metering program. The customer must first obtain written approval from the city's power department before the customer's on site generating system is energized or interconnected with the city's electric system. (Ord. 36-2015, 7-28-2015) F. In order to participate in the city's net metering program and to receive the benefits of this electric service new metering program, the customer must first sign a net metering license agreement with the city. The license agreement shall be signed by the mayor, city administrator, or power director. The interconnection and service agreement allows the customer to interconnect and operate in parallel with the city's distribution system and allows the city to test and inspect the customer's system periodically to ensure the safety of electrical workers and the integrity of the city's electric distribution system. The interconnection and service agreement will contain additional terms and conditions for service under this electric service new metering program, including specific terms of interconnection and parallel operation with the city's electrical system. (Ord. 33-2016, 5-24-2016) G. This electric service net metering program may be adjusted or discontinued by the city council for any reason, at any time, without any obligation to existing participants. (Ord. 36-2015, 7-28-2015)
Ask a question about Lehi law
Corpus searches the Lehi sections it holds and shows the ones that match, with their citations. Free, no sign-in.