9-7-4: INSPECTIONS:
The city shall have the right to inspect a customer generating facility after interconnection approval is granted, at reasonable hours and with reasonable prior notice to the customer. If the city discovers that the customer generating facility is not in compliance with the requirements of this policy, and the noncompliance adversely affects the safety or reliability of the electric distribution system, the city may require the customer to disconnect the customer generating facility until compliance is achieved. (Ord. 36-2015, 7-28-2015)