§ 31-512 — ASSURANCE FOR COMPLETION AND MAINTENANCE OF PUBLIC AND PRIVATE IMPROVEMENTS

Code of Ordinances of the City of Suffolk, Virginia (Codified through Ordinance No. 26-O-074, enacted June 17, 2026 (Supp. No. 55)) · Suffolk Unified Development Ordinance § 31-512

Corpus is an independent public-information project, not the official City of Suffolk website. Stable reference: corpuslaw.us/code/1cb69764-b5a1-4dbd-9d2f-a311e6554115

SEC. 31-512. - ASSURANCE FOR COMPLETION AND MAINTENANCE OF PUBLIC AND PRIVATE IMPROVEMENTS.

(a) GUARANTEE OF COMPLETION OF PUBLIC IMPROVEMENTS. (1) GENERALLY. The Director may accept for dedication for public use any right-of-way located within any subdivision or section thereof, which has constructed or proposed to be constructed within the subdivision or section thereof, any street, curb, gutter, sidewalk, bicycle trail, drainage or sewerage system, waterline as part of a public system or other improvement dedicated for public use, and maintained by the City, the commonwealth, or other public agency, and for the provision of other site-related improvements required by the City for vehicular ingress and egress, including traffic signalization and control, for public access streets, for structures necessary to ensure stability of critical slopes, and for storm water management facilities, financed or to be financed in whole or in part by private funds only if the owner or developer provides security in accordance with Subsection (2), below. (2) PERFORMANCE SURETY. A. The applicant shall be required to submit to the City for review and approval a cost estimate for the public improvements and shall be required to provide sufficient surety to ensure completion of the required public improvements. The amount of such certified check, cash escrow, bond, or letter of credit shall not be required to exceed the total of the estimated cost of construction based on unit prices for new public or private sector construction in the City of Suffolk and a reasonable allowance for estimated administrative costs, inflation, and potential damage to existing roads or utilities, which shall not exceed 10 percent of the estimated construction costs. If the owner or developer defaults on construction of such facilities and such facilities are constructed by the surety or with funding from the check, cash escrow, bond or letter of credit, the locality shall be entitled to retain or collect the allowance for administrative costs to the extent the costs of such construction do not exceed the total of the originally estimated costs of construction and the allowance for administrative costs. The surety shall be in the form of one or a combination of the following: (i) Furnishing to the Director a certified check or cash escrow in the amount of the estimated costs of construction or a personal, corporate or property bond, with surety satisfactory to the Director, in an amount sufficient for and conditioned upon the construction of such facilities, or a contract for the construction of such facilities and the contractor's bond, with like surety, in like amount and so conditioned; or (ii) Furnishing to the governing body a bank or savings institution's letter of credit on certain designated funds satisfactory to the governing body or its designated administrative agency as to the bank or savings institution, the amount and the form. B. In the event the City has accepted the dedication of a road for public use and such road due to factors other than its quality of construction is not acceptable into the secondary system of state highways, then the subdivider or developer shall furnish the City with a maintenance and indemnifying bond, with surety satisfactory to the Director, in an amount sufficient for and conditioned upon the maintenance of such road until such time as it is accepted into the secondary system of state highways. In lieu of such bond, the Director may accept a bank or savings institution's letter of credit on certain designated funds satisfactory to the Director as to the bank or savings institution, the amount and the form, or accept payment of a negotiated sum of money sufficient for and conditioned upon the maintenance of such road until such time as it is accepted into the secondary system of state highways and assume the subdivider's or developer's liability for maintenance of such road. "Maintenance of such road" as used in this Section, means maintenance of the streets, curb, gutter, drainage facilities, utilities or other street improvements, including the correction of defects or damages and the removal of snow, water or debris, so as to keep such road reasonably open for public usage. (3) ESCROW AGENT. If surety is provided in the form of a cash escrow, the applicant shall deposit with the Director a cash amount or certified check endorsed to the escrow agent for a face value in an amount not less than the amount specified by the Director. A. Accrual. The surety bond or cash escrow account shall accrue to the City for administering the construction, operation and maintenance of the improvements. B. Reimbursement. Where oversized facilities are required, the Director and applicant may specify a reimbursement procedure and may enter into an appropriate agreement to provide for said reimbursement to the applicant. (4) MAINTENANCE BOND (DEFECT BOND). The applicant shall file a maintenance bond with the City prior to acceptance, in a form satisfactory to the City Attorney. The amount of the bond shall be sufficient to assure the satisfactory condition of required public improvements for a period of one year after the date of their acceptance by the City and dedication to the City. If defects are found to exist within the designated period, the costs for correcting such defects shall be deducted from the maintenance bond. Any balance remaining shall be paid to the subdivider. (b) TEMPORARY IMPROVEMENTS. The applicant shall construct and pay for all costs of temporary improvements required by the Director and shall maintain said temporary improvements for the period specified. (c) RELEASE OF PERFORMANCE GUARANTEES. (1) Performance guarantees shall be released in accordance with the terms of Code of Virginia, § 15.2-2245 and this Subsection; provided, however, that to the extent that there is any inconsistency between the provisions of Code of Virginia, § 15.2-2245 and this Section, the provisions of Code of Virginia, § 15.2-2245 shall control. (2) Any bond, escrow, letter of credit, or other performance guarantee required by this Section shall be partially or finally released within 30 days after receipt of written notice by the subdivider or developer of completion of part or all of any public facilities required to be constructed hereunder unless the Director notifies the subdivider or developer in writing of nonreceipt of approval by an applicable state agency, or of any specified defects or deficiencies in construction and suggested corrective measures prior to the expiration of the 30-day period. Any inspection of such public facilities shall be based solely upon conformance with the terms and conditions of the performance agreement and the approved design plan and specifications for the facilities for which the performance guarantee is applicable, and shall not include the approval of any person other than an employee of the governing body, its administrative agency or other political subdivision or a person other than who has contracted with the governing body, its administrative agency or other political subdivision. (3) If no such action is taken by the Director within the time specified above, the request shall be deemed approved, and a partial release granted to the subdivider or developer. No final release shall be granted until after expiration of such 30-day period and there is an additional request in writing sent by certified mail return receipt to the City Manager. The Director shall act within ten working days of receipt of the request; then if no action is taken the request shall be deemed approved and final release granted to the subdivider or developer. (4) The Director shall not refuse to make a periodic partial or final release of a bond, escrow, letter of credit, or other performance guarantee for any reason not directly related to the specified defects or deficiencies in construction of the public facilities covered by said bond, escrow, letter of credit or other performance guarantee. (5) Upon written request by the subdivider or developer, the Director shall be required to make periodic partial releases of such bond, escrow, letter of credit, or other performance guarantee in a cumulative amount equal to no less than 90 percent of the original amount for which the bond, escrow, letter of credit, or other performance guarantee was taken, and may make partial releases to such lower amounts as may be authorized by the Director based upon the percentage of public facilities completed and approved by the Director. Periodic partial releases may not occur before the completion of at least 30 percent of the public facilities covered by any bond, escrow, letter of credit, or other performance guarantee. The Director shall not be required to execute more than three periodic partial releases in any twelve-month period. Upon final completion and acceptance of the public facilities, the Director shall release any remaining bond, escrow, letter of credit, or other performance guarantee to the subdivider or developer. For the purpose of final release, the term "acceptance" means: when the public facility is accepted by and taken over for operation and maintenance by the state agency, local government department or agency, or other public authority which is responsible for maintaining and operating such public facility upon acceptance. (6) For the purposes of this Section, a certificate of partial or final completion of such facilities from either a duly licensed professional engineer or land surveyor, as defined in and limited to Code of Virginia, § 54.1-400, or from a department or agency designated by the City may be accepted without requiring further inspection of such facilities.

(Ord. No. 12-O-101, 12-5-2012; Ord. No. 18-O-058, § 2(Exh. B), 6-20-2018)