§ 225.02 — Battery storage facilities/energy storage facilities

Code of the City of Virginia Beach, Virginia (Supp. No. 170: codified through Ordinance No. 3872, adopted September 1, 2026) · Virginia Beach City Code, App. A, art. 2, § 225.02

Corpus is an independent public-information project, not the official City of Virginia Beach website. Stable reference: corpuslaw.us/code/f9133a1a-5afc-4a71-a1bb-b5825aa3e9d8

Sec. 225.02. - Battery storage facilities/energy storage facilities.

(a) Application. Each application for a conditional use permit for a battery storage facility shall include the following general information: (1) Decommissioning plan. As part of the project application, the applicant shall submit a decommissioning plan, which shall include the following: a. The anticipated life of the project; b. Contact information for the party responsible for site decommissioning; c. Timeline for, and written description of, decommissioning procedures which shall include, but not limited to, removal of any above and below ground tanks, cables, fencing, debris, buildings, structures or equipment, to include foundations and pads, related to the facility and restoration land and related disturbed areas to a natural condition or other approved state. At time of approval, the city council may approve and condition a request by an applicant to have certain items intended to be utilized to serve a permitted use on the site to remain, provided site plan approval is obtained; d. "Natural condition" shall be taken to mean the stabilization of soil to a depth of three (3) feet and restoration of site vegetation and topography to its pre-existing condition, provided that the exact method and final site restoration plan shall be subject to site plan review giving, among other things, consideration to impacts upon future site use, environmental and adjacent property impacts. The director of planning or their designee may approve a request by the landowner for alternatives to site restoration to allow roads, pads or other items which will serve a future permitted site use to remain. Where applicable, if the director of planning or their designee determines that a restoration plan significantly deviates from the description and conditions approved by the city council such plan shall require amendment of the conditions by city council. (2) Project description. A narrative identifying the applicant, owner, and operator, and describing the proposed battery storage facility, including an overview of the project, its location, and maintenance plan for the project; approximate rated capacity of the battery storage facility; a description of ancillary facilities, if applicable; and analysis of the beneficial and adverse impacts of the proposed project on natural and historic resource, prime agricultural soils, or forest lands. (3) Site plan. The site plan shall conform to the preparation and submittal requirements of the city site plan review process, including supplemental plans and submissions, and shall include the following information: a. Existing and proposed buildings and structures, including preliminary location(s) of all proposed equipment; b. Existing and proposed access roads, drives, turnout locations, and parking; c. Location of any substations, electrical cabling, ancillary equipment, buildings, and structures (including those within any applicable setbacks); d. Appropriate access and water supply as required by the Fire Chief of the City of Virginia Beach; e. An emergency action plan as required by the Fire Chief of the City of Virginia Beach; and f. Fencing or other methods of ensuring public safety. (b) Special requirements. (1) Installation and maintenance of any electrical storage system (ESS) shall comply with all applicable provisions of the Virginia Building Codes and the Virginia Statewide Fire Prevention Codes. (2) When the owner or other responsible party decommissions a battery storage facility, they shall handle and dispose of the equipment and other project components in conformance with federal, state, and local requirements. (3) At such time that a battery storage facility is scheduled to be abandoned, the owner or operator shall notify the city manager or his/her designee. (4) Within three hundred sixty-five (365) days of the date of abandonment, the owner or operator shall complete the physical removal of the battery storage facility. This period may be extended at the request of the owner or operator, upon approval of the city council. (5) A one-hundred-foot setback for buildings and battery cabinet containers shall be required along all lot lines. (6) Category VI landscape screening shall be required within the setback. No other uses or structures shall be permitted in the setback. (c) Factors relating to approval. Before issuing any conditional use permit for a battery storage facility, the city council shall give due consideration to the following factors; among others: (1) The visual impact of the project, in conjunction with landscaping and screening plans; (2) Impacts to protected environmental features; and (3) An onsite fire monitoring system or fire watch prevention plan as required by the fire chief of the City of Virginia Beach. (d) Bonding requirements. The city council may require a bond or letter of credit in an amount and with surety satisfactory to the department of planning, securing to the city compliance with the conditions and limitations set forth in the conditional use permit.

(Ord. No. 3702, 7-12-22)