§ 15.05.180 — Final approval of shoreline permits

Federal Way Revised Code (The Federal Way Revised Code is current through Ordinance 26-1052, passed September 1, 2026.) · Federal Way Revised Code § 15.05.180

Corpus is an independent public-information project, not the official City of Federal Way website. Stable reference: corpuslaw.us/code/253db5d1-b906-4cf6-be65-6090a142066e

15.05.180 Final approval of shoreline permits.

(1) The director of community development shall notify and forward to the following agencies or persons within five days of the final approval of a shoreline permit and any shoreline variances or conditional uses granted: (a) The applicant; (b) The state Department of Ecology; (c) Any person who has submitted written comments on the application; and (d) Any person who has requested notification in writing prior to final approval of the permit. (2) No work may commence on a site requiring a shoreline substantial development, shoreline variance, or shoreline conditional use permit until 21 calendar days following the “date of filing” or until all review proceedings before the shoreline hearings board have terminated. (a) “Date of filing” for a substantial development permit is the date of actual receipt of the decision by the Department of Ecology. (b) “Date of filing” for a shoreline variance or shoreline conditional use permit shall mean the date the permit decision rendered by the Department of Ecology is transmitted by the department to the city and the applicant/proponent.

(Ord. No. 19-873, § 16, 7-2-19; Ord. No. 11-705, § 5 (Exh. B), 11-1-11.)