§ 10.22.130: Time of completion.

All Work covered by the Permit shall be completed by the date stated on the application. Permits shall be void if Work has not commenced 30 days after issuance, unless an extension has been granted by the Director. Bonds provided pursuant to the Tacoma Municipal Code for individual Permits will be returned after voiding of the Permit, with administrative and any other City costs deducted.

( Ord. 27834 Ex. A, 2009-09-22 )