§ 12.06.265: New large load service under 10 aMW – Schedule NLL.
A. Applicability. For new loads or expanding existing loads greater than 8 megawatts (MW) but less than 10 average megawatts (aMW) within any consecutive 12-month period. Loads receiving service under Schedule NLL may receive service under Schedule CP (or a successor rate) after a period of ten consecutive years from the beginning of service if applicable requirements are met. The customer’s initial load or subsequent load growth cannot exceed 10 aMW over any consecutive 12-month period. If a customer’s energy consumption grows by 10 aMW or more during any consecutive 12-month period, it will no longer be eligible for this rate schedule. The customer will be transitioned to Schedule Very Large Load (VLL) pursuant to subsection E of TMC § 12.06.266. B. Minimum requirements. For large power use upon the execution of a written Power Service Agreement (Contract) with Tacoma Power, which shall require among other conditions: 1. A minimum Contract Demand (as set forth in the Contract) of not less than 8 MW and not more than 10 aMW within any consecutive 12-month period; 2. Delivery of power at one primary voltage; 3. Metering at primary voltage but in no case at less than nominal 4,160 volts; 4. Power factor adjustment to 95 percent lagging or better; and 5. Service is subject to curtailment. C. Monthly rate. The sum of the following power service, delivery, customer and other charges: 1. Power service charges: (a) Energy. All energy measured in kilowatt-hours at $0.039328 per kWh. (b) Demand. All kilowatts of Billing Demand delivered at $8.48 per kW. (c) Minimum charge. The Demand Charge. (d) Contract demand overrun. A Contract Demand Overrun charge shall be imposed when the total measured demand (highest 30-minute integrated demand) exceeds the Contract Demand (as set forth in the Contract). Said charge is pursuant to the following formula: Contract Demand Overrun Charge = Excess MW x 300% x DC Where: Excess MW = MW of metered Demand in excess of the Contract Demand; DC = Demand Charge. 2. Delivery. All kilowatts of Billing Demand delivered at $9.81 per kW. 3. Customer charge. Calculated on a monthly basis, invoiced, and collected pursuant to the applicable customer service policies: $5,928.25 per month. 4. This rate schedule specifies power rates based on Tacoma Power’s system portfolio. If the customer requires additional environmental or locational attributes in power supply, additional charges including the incremental costs and Tacoma Power’s administrative costs will apply in the Power Service Agreement. D. Billing demand. Determined by means of a demand meter, 30 minute interval. 1. The Billing Demand shall be the highest of: (a) The highest measured demand for the month, adjusted for power factor; (b) 60 percent of the highest measured demand occurring during any of the preceding 11 months after adjustment for power factor; or (c) 60 percent of the highest Contract Demand (as set forth in the Contract) during any of the preceding 11 months. E. Service conditions. 1. Power factor provision applicable; and 2. Applicable provisions of the Tacoma Municipal Code, General Provisions, and Customer Service Policies governing the sale of electric energy and delivery services shall apply.
( Ord. 28707 Exs. A and B, 2020-11-24 ; Ord. 28911 Ex. A, 2023-11-21 ; ratified and reconfirmed by Ord. 28934 , 2024-01-16 ; Ord. 28993 Exs. A and B, 2024-12-03 )