§ 12.06A.100: Inspection of new electrical installations.

A. Rough-in wiring or installation of electrical equipment not listed for use in wet locations shall only be installed in a structure or area of a structure that is completely free of exposure to the elements. B. Requests for inspection must be made by the Permit Holder that installed electrical equipment no later than three business days after completion of the electrical/telecommunication installation or one business day after any part of the installation has been energized, whichever occurs first. C. Electrical wiring shall not be covered or concealed until such wiring has been approved by Tacoma Power’s Electrical Inspection Office. Where an electrical installation is covered or concealed before approval, it shall be exposed for inspection. The City shall bear no liability for damages or costs resulting from exposing the electrical installation.

( Ord. 28443 Ex. A, 2017-08-01 )