For AI agents: read the machine-readable documentation index at /llms.txt or the single-file full reference at /llms-full.txt.

§ 12.10.200 — Private contract charges

Municipal Code, City of Tacoma, Washington (Tacoma Municipal Code current through legislation adopted 2026-09-30 (eCode360 publication TA6977, scraped 2026-11-18)) · Tacoma Municipal Code § 12.10.200

Corpus is an independent public-information project, not the official City of Tacoma website. Stable reference: corpuslaw.us/code/c28992b9-559e-457c-ac63-5b42391b0765

§ 12.10.200: Private contract charges.

Extension of a permanent water main may be constructed by private contract. The developer of the privately financed project will be responsible for all costs and expenses, including any overhead and taxes incurred by the Division for preparation of plans and specifications, construction inspection, testing, flushing, sampling of the mains, and other related work necessary to complete the new water main construction to Division standards and specifications. The engineering charge for the preparation of plans and specifications will be estimated by the Division and will include all applicable permit fees. The developer will be required to pay a deposit in the amount of the estimated cost and sign an agreement acknowledging that they are responsible to pay all actual time and materials costs associated with the project. The actual costs for the work will be billed against the developer’s deposit. Should the actual costs for engineering the project exceed the deposit amount; the developer will be required to pay the balance prior to receiving the plans and specifications. Prior to construction, a second deposit in the estimated amount for construction inspection, testing, sampling and hydrant painting will be due to the Division. Upon completion of the project, the developer will either be refunded the unused amount of the deposit or billed for the cost overrun. Included in the deposits described above is a $50 per fire hydrant in the project for painting. The developer will be responsible for protecting Division facilities, including yokes and boxes, until final acceptance by the Division. After final acceptance of the project, the responsibility for the stub, yoke, box, and meter will belong to each property owner who will be charged accordingly for any damage.

( Ord. 26048 § 1, 1997-03-25 ; Ord. 27024 § 2, 2002-12-10 ; Ord. 27522 § 10, 2006-08-29 ; Ord. 27778 Ex. A, 2009-01-06 ; Ord. 29027 Ex. A, 2025-03-25 )

Ask a question about Tacoma law

Corpus searches the Tacoma sections it holds and shows the ones that match, with their citations. Free, no sign-in.