§ 12.16.120 — Time for completion—Work performed by city when—Cost

Municipal Code of the City of Casper, Wyoming (Codified through Ordinance No. 06-26, adopted July 7, 2026. (Supp. No. 97)) · Casper Municipal Code § 12.16.120

Corpus is an independent public-information project, not the official City of Casper website. Stable reference: corpuslaw.us/code/43d4494e-3d8d-49f7-9de6-58e4cb21571f

12.16.120 - Time for completion—Work performed by city when—Cost.

A. All work covered under this chapter shall be accomplished expeditiously until completion, in order to avoid unnecessary inconvenience to traffic, to pedestrians, and for the protection of other public interests. The applicant shall state, in his application for permit, the time which he estimates will be required to complete the work. Upon review of the application, the city engineer shall have the right to amend the time requested and issue the permit so as to allow the minimum amount of time which he determines will reasonably be required for such work. The time allowed for completion shall be extended as necessary if it is found that it is not possible to complete the work within the time allowed. B. In the event that the work is not being accomplished expeditiously in accordance with the time period set forth in the permit, or if the work on an excavation has ceased or is abandoned without due cause, the city engineer may, after ten working days from date of receipt give written notice to the holder of the permit of the city's intention to do so, have city forces correct the work, backfill the excavation, and effect all restoration as required by this chapter. C. In the event settlement of an excavation occurs within two years of the date of final restoration and the applicant is notified of such settlement or pavement separation, he shall accomplish the required restoration or repair within the time limit specified hereunder. Thereafter, if the work has not been accomplished, the city engineer may have city forces accomplish the work required. D. In the event city forces accomplish work in accordance with either subsections B or C above, the entire cost of such work, including any materials used therefor, shall be paid to the city by the applicant of the permit upon demand. If payment is not made within thirty days of the demand, no additional permits shall be issued to the applicant until payment has been made by the applicant or by his bonding company. In addition, the city may proceed to collect any of the costs due and owing in any manner allowed by law.

(Ord. 5-93 § 1(part), 1993: Ord. 7-88 (part), 1988; Ord. 28-83 § 1(part), 1983: prior code § 34-26)

Ask a question about Casper law

Corpus searches the Casper sections it holds and shows the ones that match, with their citations. Free, no sign-in.