15.52.030 - Permit required.
A. A solar access permit must be issued before a solar right may be established under this chapter. B. A solar access permit shall be granted for any proposed or existing solar collector which complies with the requirements of this chapter, other city ordinances and state law. C. Solar rights shall vest on the date the solar access permit is issued which date will also be the priority date of the solar right. The solar collector must be put to beneficial use within two years of that time, except additional time may be granted by the city engineer for good cause shown. The city engineer must certify the right and its beneficial use within two years of its vesting and if beneficial use has not been established, he or she will revoke the permit and record the revocation with the Laramie County clerk.
(2001 In-house code § 39-3)
Ask a question about Cheyenne law
Corpus searches the Cheyenne sections it holds and shows the ones that match, with their citations. Free, no sign-in.