PERMITS AND STREET IMPROVEMENTS
Salem Revised Code tit. VII, ch. 77
in effectSalem Revised Code § 77.020 By whom made.
Sec. 77.020. - By whom made.
All street improvements undertaken by the City in its corporate capacity shall be done by the Public Works Department.
(Prior Code, § 77.020; Ord. No. 4130; Ord. No. 51-96)
Salem Revised Code § 77.030 Posting and assessing of street improvements.
Sec. 77.030. - Posting and assessing of street improvements.
(a) Whenever the Council deems it expedient to improve any street or streets, the cost of which is to be assessed against abutting and adjacent property, the Council shall, prior to making said improvement, and in addition to all other charter requirements, cause to be posted at or near each end of the proposed street improvement a copy of a notice of intention to improve street.
(b) All abutting and adjacent property shall be assessed only for the cost of a street 34 feet in width, together with the costs of curbs, sidewalks, and drainage.
(Prior Code, § 77.030; Ord. No. 75-66; Ord. No. 51-96)
Salem Revised Code § 77.040 Duties of Director, generally.
Sec. 77.040. - Duties of Director, generally.
The Director shall prepare or approve the plans and specifications for each street to be improved, shall establish the grade and subgrade lines, and, under the direction and control of the City Manager shall see that the work is done according to plans and specifications and shall regulate the quantity and quality of each of the several ingredients constituting the paving mixture and other components used on each street.
(Prior Code, § 77.040; Ord. No. 1487; Ord. No. 51-96; Ord. No. 30-97)
Salem Revised Code § 77.050 Reserved.
Salem Revised Code § 77.060 Control of equipment; hiring and firing personnel.
Sec. 77.060. - Control of equipment; hiring and firing personnel.
The Director shall have the direction and control of such machinery and equipment as may be necessary for the use of the Department and shall have power and authority to hire and discharge such superintendents, foremen, and laborers as may be necessary or expedient on any street work undertaken by the Department.
(Prior Code, § 77.060; Ord. No. 1487; Ord. No. 51-96)
Salem Revised Code § 77.070 Direction and control of labor.
Sec. 77.070. - Direction and control of labor.
The direction and control of all labor necessary for the carrying out of the purposes of this chapter shall be under the jurisdiction of the Director.
(Prior Code, § 77.070; Ord. No. 1487; Ord. No. 51-96)
Salem Revised Code § 77.080 Record of costs.
Sec. 77.080. - Record of costs.
Adequate records shall be kept to show the total and complete cost of each improvement.
(Prior Code, § 77.080; Ord. No. 1487; Ord. No. 5338)
Salem Revised Code § 77.090 Permits required.
Sec. 77.090. - Permits required.
No person shall construct, reconstruct, repair, alter, or grade any sidewalks, curb, curb cut, driveway, street, or lay and install any sewer pipeline, water main, or stormwater facility, or attach to the City's water system without first obtaining each of the following applicable permits from the Director:
(a) Streets. A permit covering any work on public street, sidewalk, curb, curb cut, driveway within the public right-of-way, or an existing or proposed easement.
(b) Stormwater facilities. A permit covering all work to install any stormwater facilities within public right-of-way, or an existing or proposed easement.
(c) Sewer. A permit covering all work to lay and install any sanitary sewer pipeline within public right-of-way, or an existing or proposed easement.
(d) Water. A permit covering all work to lay and install any water main within public right-of-way, or an existing or proposed easement, or attach to the City's water system.
(e) Street closure. A street closure permit, if the person must obtain a permit for any of the activities identified in subsections (a) through (d) of this section, or is undertaking any activities related to the construction of a building, structure, or parking lot, and the activities require the temporary closure of a street, alley, lane of traffic, or sidewalk to vehicle or pedestrian flow.
(f) Private streets. A permit covering any work on a private street, sidewalk, curb, or curb cut.
(g) Alleys. A permit covering any work on or in a public or private alley.
(Prior Code, § 77.090; Ord. No. 132-79; Ord. No. 69-89; Ord. No. 14-92; Ord. No. 57-2000; Ord. No. 73-07; Ord. No. 34-13)
Salem Revised Code § 77.091 Approval of plans required.
Sec. 77.091. - Approval of plans required.
(a) Construction plans shall be submitted for permits required by SRC 77.090 and shall be approved by the Director, in writing, prior to issuance of the permit or permits. Subdivision improvement plans for sewer, water, streets, and stormwater conveyance and management facilities must be submitted simultaneously with such construction plans, to facilitate checking for conflicts.
(b) Construction plans shall be subject to the standards, specifications, policies and procedures, plan check, and permit fees of the Department in effect at the time of application or reapplication for plan check.
(c) Except as provided in subsection (d) of this section, plan approval shall become void upon expiration of six months from the date of written approval given under subsection (a) of this section.
(d) Upon a written finding that the facts upon which the approval was based have not changed to an extent sufficient to warrant refilling of construction plans, the Director may extend the approval period for additional extensions of six months. No more than four such six-month extensions shall be granted for any one subdivision, resulting in a maximum time extension of two years. Reapplication for plan check must be made with the Director upon expiration of each six-month period, if the permit is not issued in the initial approval period or any extension thereof.
(e) All plans, reports, or documents required by this Code shall conform to the standards set forth by the Director.
(Prior Code, § 77.091; Ord. No. 76-81; Ord. No. 176-82; Ord. No. 27-84; Ord. No. 73-07)
Salem Revised Code § 77.092 Application for plan check.
Sec. 77.092. - Application for plan check.
An application or reapplication for plan check shall be filed by the applicant with the Director for any permit or permits as required by SRC 77.090. Such application shall include:
(a) Name and address of the owner or owners of the property;
(b) Name and address of the developer of the property;
(c) Name, address, and phone number of the design engineer;
(d) Description of the work area location;
(e) Attached two sets of preliminary plans showing a vicinity map and details of the proposed project, including street widths and property lines, grades, existing and proposed ground profiles, contours, drainage plan with contours, hydraulic calculations, soil boring logs and appropriate soils report, prepared by a registered civil engineer licensed by the State and shall be signed by him or her and stamped with his or her seal to indicate his or her responsibility for them;
(f) Evidence that all federal and state laws and regulations have been complied with, including a copy of permits required by federal, state, or county agencies;
(g) Engineer's estimated construction cost of the proposed project;
(h) Such other information as the Director shall find reasonably necessary for the determination of whether plans should be approved for permit.
(Prior Code, § 77.092; Ord. No. 76-81; Ord. No. 57-2000)
Salem Revised Code § 77.093 Plan review service fees.
Sec. 77.093. - Plan review service fees.
(a) Accompanying the application or reapplication required by SRC 77.092 shall be a service fee as prescribed by resolution of the Council.
(b) Fees provided in subsection (a) of this section are intended to support permit plan review.
(Prior Code, § 77.093; Ord. No. 76-81; Ord. No. 107-84; Ord. No. 51-91; Ord. No. 51-96)
Salem Revised Code § 77.100 Application.
Sec. 77.100. - Application.
Any applicant for a permit as required by SRC 77.090 shall file an application with the Director. Such applications shall include:
(a) Name and address of the owners of the property;
(b) Name and address of the developer of the property;
(c) Name and address of the engineer;
(d) Name and address of the party doing the work;
(e) Location of the work area;
(f) Six sets of approved plans, specifications, and easements required, accompanied by a drawing showing area covered by said legal description;
(g) Evidence that all federal and state laws and regulations have been complied with;
(h) Proposed work schedule, provided that any changes in this work schedule shall be filed with the City;
(i) Estimated itemized cost of the proposed project;
(j) Such other information as the Director shall find reasonably necessary for the determination of whether a permit should be issued therefor.
(Prior Code, § 77.100; Ord. No. 132-79; Ord. No. 76-81; Ord. No. 57-2000)
Salem Revised Code § 77.110 Permit fees.
Sec. 77.110. - Permit fees.
(a) Accompanying the application required by SRC 77.100 for each category shall be a permit fee as prescribed by resolution of the Council.
(b) Fees listed in subsection (a) of this section are fixed and nonrefundable, and are required to support permit issuance, testing, and inspection.
(c) In computing the permit fees, the estimated value of proposed construction shall be comparable with current bid prices for City contract projects and approved prior to issuing the permit.
(d) Work being done under contract with the City shall be exempt from the provisions of SRC 77.090 to 77.120.
(e) Where work for which a permit is required by this Code is commenced or proceeded with prior to obtaining said permit, the fees specified in subsection (a) of this section shall be doubled, but the payment of such double fee shall not relieve any person from fully complying with the requirements of this Code in the execution of the work nor from any other penalties prescribed herein.
(f) Permits required by SRC 77.090 shall be nontransferable. Any change in applicant, such as a subdivision sale, will require reapplication for permit. If six months has elapsed since plan approval required by SRC 77.091, reapplication for plan check shall be made.
(Prior Code, § 77.110; Ord. No. 173-78; Ord. No. 132-79; Ord. No. 76-81; Ord. No. 107-84; Ord. No. 69-89; Ord. No. 51-91; Ord. No. 51-96)
Salem Revised Code § 77.120 Bonds or other written evidence to be filed; final acceptance.
Sec. 77.120. - Bonds or other written evidence to be filed; final acceptance.
(a) No permit shall be issued pursuant to SRC 77.100 unless there is filed with the application a performance guarantee in the form specified in SRC 110.100, sufficient to satisfy the Director that the work shall be done in accordance with City standards and specifications.
(b) The Director shall require an applicant to file satisfactory evidence of insurance protecting and saving harmless the City, its officers, agents, and employees from all claims for damages or injury to other persons by reason of such alteration work prior to acceptance and for a period of one year thereafter. Such insurance shall be in not less than the amounts specified in ORS 30.272, and the evidence thereof shall be in a form approved by the City Attorney.
(c) Prior to final acceptance and start of one-year warranty period, the private engineer for the project must submit the following:
(1) As-built drawings, consistent with Public Works Design Standards, prepared and certified by a registered professional engineer licensed by the State;
(2) All additional easements required due to construction changes, accompanied by a drawing showing area covered by said legal description;
(3) A maintenance bond or other written evidence in a form approved by the City Attorney guaranteeing the work performed for a period of one year after completion of the project and written acceptance by the Director. The maintenance bond may be incorporated in and made a part of the construction bond;
(4) Such other information as the Director shall deem necessary for final acceptance.
(d) Prior to final acceptance and start of the one-year warranty period for a sanitary sewer project, the project engineer shall notify the Director that the system is complete and ready for final inspection. The Director shall cause inspection of the system by means of a closed circuit TV camera to ensure that there are no cracks in the pipe, that all joints are tight, that deflection is within acceptable tolerances, and that there are no conditions apparent which would permit the infiltration of groundwater into the system.
(e) Prior to final acceptance and start of the one-year warranty period for a project other than a sanitary sewer project, the Director shall cause such inspection of the project as the Director may consider necessary.
(Prior Code, § 77.120; Ord. No. 103-76; Ord. No. 132-79; Ord. No. 74-81; Ord. No. 93-84; Ord. No. 79-85; Ord. No. 31-13)
Salem Revised Code § 77.122 Governmental agency agreement in lieu of guarantees.
Sec. 77.122. - Governmental agency agreement in lieu of guarantees.
Subject to any conditions imposed by the Director, a governmental agency may, in lieu of those guarantees required by SRC 77.120(a), guarantee in writing that all work will be done in accordance with City standards and in accordance with the plans approved by the Director and shall indemnify the City for all costs of completing or correcting the work should that become necessary.
(Prior Code, § 77.122; Ord. No. 85-86)
Salem Revised Code § 77.130 Notice before commencement of work.
Sec. 77.130. - Notice before commencement of work.
At least 48 hours' notice shall be given by the contractor of intention to begin work after issuance of a permit required by SRC 77.090. In the event of temporary cessation of work activities, such notice shall be required before the resumption of any additional work.
(Prior Code, § 77.130; Ord. No. 131-69; Ord. No. 132-79)
Salem Revised Code § 77.140 Suspension of permit; stop work order; appeal.
Sec. 77.140. - Suspension of permit; stop work order; appeal.
(a) At any time after the issuance of a permit required by SRC 77.090, the Director may suspend the same upon a finding that any of the following grounds exist:
(1) False, misleading, or erroneous data or information submitted by the applicant in connection with securing the permit.
(2) Materials or workmanship which do not meet specification for the construction or installation of the permitted improvement; or construction or installation which varies from the approved plan or design of the improvements.
(3) Violation of any of the provisions of this Code governing the work being done under the permit.
(b) Upon suspension of a permit as provided in subsection (a) of this section, the Director shall cause to be issued a written stop work order, one copy of which shall be sent by regular mail to the permittee at the address shown on the permit application, one copy of which shall be sent by regular mail to the permittee's engineer overseeing the work, if known, and one copy of which shall be personally delivered to the person in charge of any work in progress.
(c) It shall be unlawful for any person to cause, suffer, or permit any work to be done for which a permit is required by SRC 77.090 when a stop work order has been issued as provided in subsection (b) of this section.
(d) Any person whose permit has been suspended as provided in subsection (a) of this section may appeal such action to the Hearings Officer as provided in SRC chapter 20J. Notwithstanding the provisions of SRC chapter 20J, the filing of an appeal shall not stay the effect of a stop work order issued under subsection (b) of this section.
(Prior Code, § 77.140; Ord. No. 115-79)
Salem Revised Code § 77.150 Reserved.
Salem Revised Code § 77.160 Sidewalk improvement requirements.
Sec. 77.160. - Sidewalk improvement requirements.
(a) Public Works Design Standards. Construction of sidewalks conforming to the Public Works Design Standards shall be a condition of the issuance of any building permit for a development located on property lacking such sidewalks. As used in this section, the term "development" means the construction or enlargement of any building or structure requiring a building or occupancy permit under SRC chapter 56, but excluding building permits for improvements to existing single family or duplex dwelling unit structures under the following conditions:
(1) The existing single family or duplex dwelling unit structure is located on property abutting an unimproved street that lacks curbs;
(2) The proposed development is less than a 50 percent enlargement of the existing floor area square footage of the structure, including an attached garage; and
(3) The conversion of, or addition to, an existing single family detached dwelling to create a duplex, triplex, or quadplex when:
(A) The existing single family detached dwelling is located on property abutting an unimproved street that lacks curbs; or
(B) The proposed development is less than a 50 percent enlargement of the existing floor area square footage of the structure, including an attached garage.
(b) Deferral, City required. Construction of required sidewalks may be deferred at no cost where street improvements are anticipated or where no sidewalks are presently located within 150 feet and on the same side of the adjacent property.
(c) Alternative street standard and enforcement. Alternatives from and enforcement of the requirements of this section shall be as provided in SRC 803.065 and 78.300.
(Prior Code, § 77.160; Ord. No. 91-99; Ord. No. 72-2002; Ord. No. 31-13; Ord. No. 13-21, § 1(Exh. A), 2-14-2022)
Salem Revised Code § 77.170 Construction of traffic signals by private developers.
Sec. 77.170. - Construction of traffic signals by private developers.
A developer may qualify for partial reimbursement for the construction of a new traffic signal by meeting all of the requirements under the provisions of SRC 77.180 to 77.230. Only signals that are recommended in a traffic impact analysis and required as an off-site transportation improvement will be eligible for reimbursement under the provisions of this chapter. Signals eligible for full reimbursement with transportation system development charges, constructed for the express purpose of improving access to private property, or in which one or more legs of the intersection is a private driveway, shall not be eligible for reimbursement.
(Prior Code, § 77.170; Ord. No. 8-2003)
Salem Revised Code § 77.180 Filing for preliminary consent.
Sec. 77.180. - Filing for preliminary consent.
(a) The developer shall file with the Director a complete traffic impact analysis. The traffic impact analysis shall include a request to construct the traffic signal, setting forth the proposed location of the traffic signal, the purpose for which it is to be constructed, and a request for reimbursement.
(b) The Director shall review the proposal and render a decision to allow for reimbursement within 30 days of the developer's application.
(c) No later than six months after receiving consent from the Director for the proposed traffic signal and a preliminary determination that reimbursement will be allowed under SRC 77.190, the developer may file an application with the Director as provided in SRC 77.190.
(Prior Code, § 77.180; Ord. No. 8-2003)
Salem Revised Code § 77.190 Application by developer.
Sec. 77.190. - Application by developer.
(a) A developer who has received the Director's consent to construct a traffic signal that is eligible for reimbursement and desires to proceed therewith, shall make application with the Director, and provide the following information:
(1) Detailed plans and specifications conforming to adopted standards of the City;
(2) Cost estimates for the project, certified to by a professional engineer;
(3) Legal description of all property that may need to be acquired to construct the signal and the property owners' names and addresses;
(4) Name of the contractor who will be installing the signal;
(5) A current turning movement count at all legs of the intersection;
(6) An estimate of the developer's additional new trips that will use the traffic signal;
(7) Listing of all property owners of all undeveloped and underdeveloped properties that could generate 50 or more analysis hour trips through the signal; and
(8) Such other information the Director deems necessary to evaluate the application.
(b) Upon submittal of an application, the Director shall determine if the application is complete and grant final approval. Approval shall be withheld for incomplete applications. The Director's decision regarding completeness of the application shall be final on the matter.
(Prior Code, § 77.190; Ord. No. 8-2003)
Salem Revised Code § 77.200 Construction approval.
Sec. 77.200. - Construction approval.
Upon approval of the application by the Director and execution of an improvement agreement and issuance of a construction permit, the developer may proceed with the construction of the traffic signal in accordance with the approved plans and specifications. The developer shall notify the Director when construction commences and the construction shall be completed within one year of the date of the approval. All required permits shall be obtained by the developer or developer's contractor prior to commencing construction.
(Prior Code, § 77.200; Ord. No. 8-2003)
Salem Revised Code § 77.210 Filing statement of cost by developer.
Sec. 77.210. - Filing statement of cost by developer.
(a) Upon completion of the traffic signal installation, the developer shall file with City Engineer an itemized cost statement thereof. In addition to actual construction costs, costs associated with design, production of construction documents, permitting, bonding, and any other costs associated with the design of the signal, as well as right-of-way acquisition, signal interconnect, street lighting directly associated with the signal, and other materials directly related to the installation of the signal shall be eligible for reimbursement.
(b) If the total cost shown on the itemized statement exceeds the estimate in the approved application, the Director may approve the overage for the purposes of calculating the pro-rata share reimbursements if the Director is satisfied the overage was due to conditions not readily foreseen at the time of the construction.
(Prior Code, § 77.210; Ord. No. 8-2003)
Salem Revised Code § 77.220 Apportioning the cost of the traffic signal project.
Sec. 77.220. - Apportioning the cost of the traffic signal project.
(a) The developer shall be entitled to reimbursement of a pro-rata share of the project cost from each property benefitted from the installation of the traffic signal.
(b) For the purposes of this section, "property benefitted" is any development built within ten years of the start of the signal operation which is required to prepare a traffic impact analysis and which generates 50 or more analysis hour trips through the new signal.
(c) The pro-rata share for each development shall be calculated by dividing each development's trips into the sum of the trips pursuant to SRC 77.190(a)(5) and (6), and multiplied by the final construction costs approved pursuant to SRC 77.210.
(d) The pro-rata share of the cost determined under subsection (c) of this section shall be annually adjusted (indexed) for inflation using the Engineering News Record (ENR) index adopted by the Council for the systems development charge methodology pursuant to SRC 41.170(e).
(Prior Code, § 77.220; Ord. No. 8-2003)
Salem Revised Code § 77.230 Reimbursement of developer.
Sec. 77.230. - Reimbursement of developer.
Reimbursement to any person constructing a qualified public improvement shall be as provided in SRC 41.300 and 41.305.
(Prior Code, § 77.230; Ord. No. 8-2003)
Salem Revised Code § 77.990 Violations.
Sec. 77.990. - Violations.
Violation of SRC 77.090 is an infraction.
(Prior Code, § 77.990; Ord. No. 193-79)
Source: City of Salem, Oregon, Salem Revised Code and City Charter (Municode Library, library.municode.com)URL: https://library.municode.com/or/salem/codes/code_of_ordinances?nodeId=PTIICOOR_TITVIIPESTPUWA_CH77PESTIMFetched: 11/7/2026