Sec. 75.175. - Stop work orders; permit revocation; civil penalties; enforcement.

(a) Stop work orders and permit revocation. (1) The Director may suspend work or revoke an erosion control permit upon a finding that: (A) The work is not authorized by a valid permit; (B) Inaccurate information was used to obtain the permit; (C) The applicant is not complying with the terms of the permit or the provisions of this chapter; or (D) The work is, or threatens to become, a hazard to property or public safety; is adversely affecting or about to adversely affect adjacent property or rights-of-way, a drainage way, waterway, wetlands, fish or wildlife habitat, or a stormwater facility; or is otherwise adversely affecting the public health, safety, or welfare. (2) The Director shall issue a written notice specifying the nature of the violation or problem which must be remedied prior to resuming other work on the project. (3) Persons violating this chapter, or a permit issued hereunder, shall be responsible for restoring damaged areas in conformance with a plan approved by the Director which provides for repair of any environmental or property damage and restoration of the site. The plan shall result in conditions upon the site which, to the greatest extent practical, equal the conditions that would have existed had the violation not occurred, as verified by a certified professional. (b) Civil penalty. Any person who fails to comply with the requirements of this chapter, or the terms of a permit issued hereunder, who undertakes an activity regulated by this chapter without first obtaining a permit, or who fails to comply with a stop work order issued pursuant to this chapter shall also be subject to a civil penalty, not to exceed $2,000.00 per violation. Each day that a permit violation continues shall constitute a separate violation. (c) Civil penalties against agents. Any person who acts as the agent of, or otherwise assists, a person who engages in an activity which would be subject to a civil penalty, may likewise be subject to a civil penalty. (d) Prohibition of further approvals; injunctive relief. (1) The City shall not issue a Notice of Final Completion for property on which a violation of this chapter has occurred or is occurring, until the violation has been cured by restoration or other means acceptable to the Director and any penalty imposed for the violation is paid. (2) The City may seek injunctive relief against any person who has willfully engaged in a violation of SRC 75.030, 75.050, 75.070, 75.090, 75.120, 75.130, 75.140, 75.150, 75.160, 75.170, and 75.200, such relief to be in effect for a period not to exceed five years. (e) Appeals. Any person affected by any decision, action, or determination made by the Director, interpreting or implementing the provisions of this chapter, may file a written request for reconsideration with the Director within ten days of such decision, action, or determination, setting forth in detail the facts supporting the person's request for reconsideration. The Director's final order upon reconsideration may be appealed to the Hearings Officer by filing a written notice of appeal no later than ten days after notification of the Director's final order. The Director's final order shall remain in effect during such pendency of reconsideration and appeal.

(Prior Code, § 75.175; Ord. No. 26-06)