§ 17-9 — Best management practices—Tier 1 land disturbance permit
Code of the City of Mobile, Alabama (Supp. No. 67: codified through Ordinance No. 36-017-2026, adopted March 1, 2026) · Mobile City Code § 17-9
Corpus is an independent public-information project, not the official City of Mobile website. Stable reference: corpuslaw.us/code/d249f531-25f9-453f-b970-4ad15447352e
Sec. 17-9. - Best management practices—Tier 1 land disturbance permit.
(a) Design and performance standards. The following are required for all land-disturbing activities that require a tier 1 land disturbance permit, see section 17-8(b), and will take effect three hundred sixty-five (365) days following the effective date of the city NPDES ALS000007 permit for its MS4. All applications for a land disturbance permit must contain, or be accompanied by, the materials and information necessary to satisfy the requirements of this division and must be accompanied by a construction best management practices (CBMP) plan. The CBMP plan shall be prepared by a qualified credentialed professional and shall include the following: (1) The CBMP shall be accompanied by an engineering map or plan of the property upon which land-disturbing activities are to be conducted, prepared by a registered engineer or land surveyor, showing the present contour lines of such property, and the present contour lines of at least the nearest twenty-five (25) feet of the properties immediately adjacent to such property and the existing grades and evaluations of all streets which abut such property. Such map or plan shall show all existing drainage facilities and all natural drainage on such property and on such adjacent property. (2) All proposed contours, the proposed temporary and permanent disposition of surface water and the proposed drainage structures. (3) The proposed contours in the map or plan shall be depicted in contour intervals of a minimum of one (1) foot. All maps and plans submitted shall be on a standard sized sheet twenty-four (24) inches by thirty-six (36) inches and drawn to a scale of not less than one (1) inch equals one hundred (100) feet. Contour intervals of more than one (1) foot and maps or plans which are smaller than the standard size may be approved by the city engineer, upon written request and for good cause shown. All sheets will be standard paper sizes. (4) The CBMP plan shall contain a description of the existing site conditions, a description of adjacent topographical features, the information necessary to determine the erosion qualities of the soil on the site, potential problem areas of soil and erosion and sedimentation, soil stabilization specifications, stormwater management considerations, a sequence of construction and projected time schedule for the commencement and completion of the land-disturbing activity, specifications for CBMP plan maintenance during the project and after completion of the project, clearing and grading limits, and all other information needed to depict accurately the solutions to potential soil erosion and sedimentation problems to the MS4. The CBMP plan shall include the series of BMPs and shall be reviewed by, and subject to the approval of, the city engineer prior to the issuance of the tier 1 land disturbance permit. An ADEM notice of registration (NOR) shall be submitted with the application. The notice of intent (NOI) may be provided until the NOR is received from ADEM. Copies of all monitoring data and reports shall be submitted to the city in the same manner as they are submitted to ADEM and in the frequency specified by the city. (5) Where appropriate, in the opinion of the qualified credentialed professional who prepares the CBMP plan, to the maximum extent practicable, the CBMP plan shall include measures to reduce erosion and other adverse impact to MS4 drainage which would result from an increase in the volume of water and the rate of runoff of water during the conduct of land-disturbing activities. (6) Whenever the city engineer determines that a CBMP plan does not comply with this division, he shall notify the applicant in writing of the ways in which the CBMP plan does not comply with this division. (7) To the maximum extent practicable, sediment in runoff water must be minimized by using appropriate BMPs. (8) Structural controls shall be designed by a registered Alabama professional engineer. Structural controls shall be designed and maintained as required to minimize erosion and pollution to the maximum extent practicable. All surface water flowing toward the construction area shall, to the maximum extent practicable, either be passed through the site in a protected channel or diverted by using berms, channels or sediment traps, as necessary. Erosion and sediment control measures shall be designed, according to the size and slope of the disturbed areas or drainage areas, to minimize erosion and to control sediment, to the maximum extent practicable. Discharges from sediment basins and traps must be conducted in a manner consistent with good engineering practices. Sediment-laden, or otherwise polluted, water discharged to the MS4 must be addressed in a manner consistent with good engineering practices and the requirements of this division. (9) Control measures shall be maintained as an effective barrier to sedimentation and erosion in accordance with the provisions of this division. (10) There shall be no distinctly visible floating scum, oil or other matter contained in the stormwater discharge. The stormwater discharge to an MS4 must not cause an unnatural color (except dyes or other substances discharged to an MS4 for the purpose of environmental studies and which do not have harmful effect on the bodies of water within the MS4) or odor in the community waters. The stormwater discharge to the MS4 must result in no materials in concentrations sufficient to be hazardous or otherwise detrimental to humans, livestock, wildlife, plant life or fish and aquatic life in the community waters. (11) When the land-disturbing activity is finished and stable vegetation or other permanent controls have been established on all remaining exposed soil, the owner of the land where the land-disturbing activity was conducted, or his authorized agent, shall notify the city of these facts, and request a final inspection. The city shall then inspect the site within five (5) working days after receipt of the engineer's as-built certification, see section 17-7(o), and may require additional measures to stabilize the soil and control erosion and sedimentation. If additional measures are required by the city, written notice of such additional measures shall be delivered to the owner, and the owner shall continue to be covered by the land disturbance permit issued with respect to the land-disturbing activity until a final and complete inspection is made to the satisfaction of the city. The owner's professional engineer shall certify to the city that land-disturbing activity is finished and stable, and vegetation or other permanent controls have been established on all remaining exposed soil for the site. Following receipt of an acceptable final engineer's as-built certification of the project and satisfactory inspection, the city will deliver to the owner, within ten (10) days of the date of such certification, a sign-off will be entered in the permitting system showing that the erosion control requirements of the land disturbance permit have been fulfilled. At that time, the site and/or the project constructed thereon may come under the operation of other ordinances of the city. (12) The CBMP plan must be accompanied by a letter of credit, a surety bond or a cash bond, with the city having the right to determine which type of security shall be furnished. Unless the city determines that sufficient security for compliance with the requirements of this division is already in place, a letter of credit, a surety or a cash bond (a letter of credit, a surety bond and a cash bond shall be herein collectively referred to as "security") shall be furnished to the city in accordance with the following provisions: a. The city shall require a letter of credit, a surety bond or a cash bond in such amount as specified herein to assure that the work, if not completed or if not in accordance with the permitted plans and specifications will be corrected to eliminate hazardous conditions, erosion and/or drainage problems. In lieu of a letter of credit or a surety bond required by the city, the owner may file a cash bond with the city in an amount equal to that which would be required in the letter of creditor or the surety bond. b. The security shall contain, or have attached to it as an exhibit, a legal description of the site. The security shall remain in effect for such reasonable period of time as may be required by the city. c. The security for clearing operations only shall be in the amount of one thousand dollars ($1,000.00) per acre for each acre, or fraction of an acre, disturbed or affected by such operations. d. The security for earthwork or clearing and earthwork operations shall be in the amount of three thousand dollars ($3,000.00) per acre for each acre, or fraction of an acre, disturbed or affected by such operations. e. Security equal to double the amounts required in subsections (3) and (4) herein, shall be required where clearing or earthwork is performed in areas designated as flood ways, floodplains or areas susceptible to landslides. f. Each letter of credit must be issued by a bank which has its principal office in the city. g. Each letter of credit must be issued by a bank which is reasonably satisfactory to the city and each surety bond must be issued by a surety company which is qualified to do business in the state and which is otherwise reasonably satisfactory to the city. (b) Notice of construction commencement and construction inspections for tier 1 land disturbance permits. (1) Notice of construction commencement. The permittee under a tier 1 land disturbance permit must notify the city in advance before the commencement of construction. (2) Construction inspections. Regular inspections of the stormwater management system construction shall be conducted by a certified professional engineer, or a qualified certified inspector ("QCI") or qualified credentialed professional ("QCP"). All inspections shall be documented and written reports prepared that contain the following information: a. The date of the inspection; b. Whether construction complies with the approved CBMP plan; c. Any deviation from the approved construction specifications; and d. Any violations of the stormwater and flood control ordinance. e. Any violations will be processed in accordance with section 17-14 of this division. (3) Final inspection—Submittal of "as-built" plans. Permittees are required to submit "as-built" plans for any stormwater management practices located on-site after final construction is completed in CAD form. The plan must show the final design specifications for all stormwater management facilities and must be certified by a professional engineer. No performance securities will be released before the city engineer or his agent completes a final inspection and approval of the stormwater management facilities. (c) Land stabilization requirements for tier 1 land disturbance permits. (1) Any land surface from which the natural vegetative cover has been either partially or wholly cleared or removed by development activities shall be revegetated within ten (10) days from the substantial completion of clearing and construction, see section 17-6(1) of this division. Revegetation must meet the following criteria: a. All reseeding must use an annual or perennial cover crop accompanied by placement of straw mulch or its equivalent of sufficient coverage to control erosion until such time as the cover crop is established over ninety (90) percent of the seeded area. Reseeding can be accomplished with solid sodding (Bermuda). b. Detention ponds must be solid sodded. c. When replanting with native woody and herbaceous vegetation, the ground must be covered by straw mulch or its equivalent in an amount of sufficient coverage to control erosion until the plantings are established and capable of controlling erosion. d. Any area of revegetation must exhibit survival of a minimum of seventy-five (75) percent of the cover crop throughout the year immediately following revegetation. Revegetation must be repeated in successive years until the minimum seventy-five (75) percent survival for one (1) year is achieved. (2) A landscaping plan must be submitted with the final design describing the temporary and permanent vegetative stabilization and management techniques to be used at a site for construction. This plan will not only explain how the site will be stabilized after construction, but also identify who will be responsible for the maintenance of vegetation at the site and what practices will be employed to ensure that adequate vegetative cover is preserved. This plan must be prepared by a registered QCP or professional engineer licensed by the state and must be approved prior to receiving a permit reporting compliance with plan. (d) Waivers of stormwater management requirements. (1) Every applicant for a tier 1 land disturbance permit shall provide for stormwater management both during construction and post-construction as required by this division, unless a written request is filed to waive this requirement. Requests to waive the stormwater management plan requirements shall be submitted to the city engineer for approval. (2) The minimum requirements for stormwater management may be waived in whole or in part upon written request of the applicant, provided that at least one (1) of the following conditions applies: a. It can be determined that the proposed development is not likely to impair attainment of the objectives of this division. b. Alternative minimum requirements for on-site management of stormwater discharges have been established in a stormwater management plan approved by the city engineer and implemented pursuant to this division. c. Provisions are made to manage stormwater through an off-site facility. The off-site facility is required to be in place, to be designated and adequately sized to provide a level of stormwater control that is equal to or greater than that which would be afforded by on-site practices and there is a legally obligated entity responsible for long-term operation and maintenance of the stormwater practice. d. The city engineer finds that meeting the minimum on-site management requirements is not feasible due to the natural or existing physical characteristics of the site. e. Non-structural practices will be used on the site that reduce: 1. The generation of stormwater from the site; and 2. The size and cost of stormwater storage; and the pollutants generated at the site. f. The city will not grant a waiver if to do so would cause any of the following impacts to downstream waterways: 1. Deterioration of existing culverts, bridges, dams, or other structures, or any element of the city's MS4, private water courses, waters of the state or of the United States; 2. Degradation of biological functions or habitat; 3. Accelerated streambank or streambed erosion or siltation; 4. Increased threat of flood damage to public health, life, property. g. In order to be eligible for a waiver, the applicant must complete a mitigation measure, which may include but is not limited to one (1) of the following: 1. The purchase and donation of privately owned lands, or the grant of an easement to be dedicated for preservation and/or reforestation. These lands should be located adjacent to the stream corridor in order to provide permanent buffer areas to protect water quality and aquatic habitat. The donation shall run with the land, and shall be recorded in the records of the office of the probate court, Mobile County. 2. The creation of a stormwater management facility or other drainage improvements on previously developed properties, public or private, that currently lack stormwater management facilities designed and constructed in accordance with the purposes and standards of this division. 3. Payment of a fee in lieu of stormwater practices may be accepted when implementation of otherwise applicable stormwater practices is impracticable under the provisions of this subsection. The fee will be determined according to a fee schedule established by the city based on the size and type of the development activity.
(Ord. No. 17-013-2020, 5-19-20)
Ask a question about Mobile law
Corpus searches the Mobile sections it holds and shows the ones that match, with their citations. Free, no sign-in.