§ 8-107 — Construction documents
The Code of the City of Tempe, Arizona (Supp. No. 34, Update 1: codified through Ordinance No. O2026.34, enacted June 25, 2026) · Tempe City Code § 8-107
Corpus is an independent public-information project, not the official City of Tempe website. Stable reference: corpuslaw.us/code/e3a7d829-2f0f-4777-97ae-b4ee6b678e80
Sec. 8-107. - Construction documents.
107.1 General. Submittal documents consisting of construction documents, statement of special inspections, geotechnical report, specifications, engineering calculations, diagrams, and other data, as required by the building official, shall be submitted with each application for a permit. The construction documents shall be prepared by a registered design professional as required by state law. Where special conditions exist, the building official is authorized to require additional construction documents to be prepared by a registered design professional. Exception: The building official is authorized to waive the submission of construction documents and other data not required to be prepared by a design professional if it is found that the nature of the work applied for is such that review of construction documents is not necessary to obtain compliance with this code, the City of Tempe Construction Codes and other ordinances of the City. 107.2 Construction documents. Construction documents shall be in accordance with Sections 107.2.1 through 107.2.4 of this code. 107.2.1 Information on construction documents. Construction documents shall be dimensioned, drawn to scale and shall be submitted electronically through the city's permitting portal. Construction documents shall be of sufficient clarity to indicate the location, nature and extent of the work proposed and show in detail that it will conform to the provisions of this code, the City of Tempe Construction Codes, relevant laws and ordinances as determined by the building official. 107.2.2 Title sheet information. The construction documents shall contain a title sheet or title sheets indicating the name, address and phone numbers of designer(s). The title sheet shall also contain information regarding the code designed under, the size of the building, size of addition (if applicable), type of construction (when designed to IBC), occupancy classification(s), occupant load (when designed to the IBC), area and height modifications (if any), fire sprinklers (if any), and any other information as directed by the building official. The building official is authorized to waive or modify the requirement for a title sheet when the application for permit is for an alteration or repair or when otherwise warranted. 107.2.3 Site plan. The construction documents submitted with the application for permit shall be accompanied by a site plan showing to scale the size and location of new construction and existing structures and conditions on the site, distances from lot lines, and it shall be drawn in accordance with an accurate boundary line survey. In the case of demolition, the site plan shall show construction to be demolished and the location and size of existing structures and construction that are to remain on the site or plot and any other requirements detailed in chapter 1 of the City of Tempe Construction Codes. The building official is authorized to waive or modify the requirement for a site plan when the application for permit is for an alteration or repair or when otherwise warranted. 107.2.4 Other Requirements. Plans shall include any requirements found in each chapter 1 of the City of Tempe Construction Codes the project is designed to. 107.2.5 Means of egress. The construction documents shall show in sufficient detail the location, construction, size and character of all portions of the means of egress including the path of the exit discharge to the public way in compliance with the provisions of the Technical Codes. In other than Group R-2, R-3 and I-1 occupancies, the construction documents shall designate the number of occupants to be accommodated on every floor, and in all rooms and spaces. The building official is authorized to waive or modify the requirement for a means of egress plan when the application for permit is for an alteration or repair or when otherwise warranted. 107.3 Examination of documents. The building official shall examine or cause to be examined the permit application and accompanying construction documents and shall ascertain by such examinations whether the construction indicated and described is in accordance with the requirements of this code, the City of Tempe Construction Codes and other pertinent laws or ordinances. 107.3.1 Administrative Completeness Review. Submittal documents may be subject to screening by the building official for completeness and code compliance prior to being accepted for permit review. Incomplete submittals or submittals containing clear code violations shall be returned to the applicant without being accepted unless otherwise directed by the building official. 107.3.2 Approval of construction documents. When the building official issues a permit, the construction documents shall be approved, in writing or by stamp, as "Reviewed for Code Compliance." A digital set of construction documents so reviewed shall be retained by the building official as required by the approved Building Safety Division retention schedule. A digital set shall be made available to the applicant through the permitting portal, and shall be made available at the site of work and shall be open to inspection by the building official or a duly authorized representative. 107.3.3 Previous approvals. This code and the City of Tempe Construction Codes shall not require changes in the construction documents, construction or designated occupancy of a structure for which a lawful permit has been heretofore issued or otherwise lawfully authorized, and the construction of which has been pursued in good faith within one hundred eighty days after the permit issuance date and has not been abandoned pursuant to this code and the City of Tempe Construction Codes. 107.3.4 Phased approval. With prior approval from the building official, an applicant may apply for and the building official may authorize the issuance of a permit for the construction of foundations, or other parts of a building or structure before the construction documents for the whole building or structure have been submitted, provided adequate information and detailed statements have been filed complying with pertinent requirements of this code and the City of Tempe Construction Codes. The holder of such permit for the foundation or other parts of a building or structure shall proceed at the holder's own risk with the building operation and without assurance that a permit for the entire structure will be granted. Exception: Phased construction approvals are not applicable for Group R-3, R-4, Detached Single Family, Two Family and Townhome occupancies. 107.3.5 Design professional in responsible charge. Where it is required that the documents be prepared by a registered design professional, the building official shall be authorized to require the owner or owner's authorized agent to engage and designate on the building permit application a registered design professional who shall act as the registered design professional in responsible charge. If the circumstances require, the owner or the owners authorized agent shall designate a substitute registered design professional in responsible charge who shall perform the duties required of the original registered design professional in responsible charge. The building official shall be notified in writing by the owner or the owners authorized agent if the registered design professional in responsible charge is changed or is unable to continue to perform the duties. The registered design professional in responsible charge shall be responsible for reviewing and coordinating submittal documents prepared by others, including phased and deferred submittal items, for compatibility with the design of the building. 107.3.5.1 Deferred submittals. Deferral of any submitted item shall have the prior approval of the building official. The registered design professional in responsible charge shall list the deferred submittals on the title sheet of the construction documents for review by the building official. Unless otherwise approved by the building official, deferred submittals are to be submitted to the building official within sixty days of permit issuance. Deferred submittal items shown on the construction documents shall be clearly noted as "For Reference Only". Deferred submittals do not constitute phased approval of the construction. Documents for deferred submittal items shall be submitted to the registered design professional in responsible charge who shall review them and forward them to the building official with a notation indicating the deferred submittal documents have been reviewed and been found to be in general conformance to the design of the building. The deferred submittal items shall not be installed until the design and submittal documents have been approved by the building official. 107.4 Amended construction documents (Revisions). Work shall be installed in accordance with the approved construction documents, and any changes made during construction that are not in compliance with the approved construction documents shall be resubmitted for approval as an amended set of construction documents. 107.5 Retention of construction documents. Approved construction documents shall be retained by the building official for a period of time as prescribed by state or local laws. 107.6 Responsibility. It shall be the duty of every person who performs work for the installation or repair of building, structure, electrical, gas, mechanical, plumbing, or fire-suppression systems, for which this code or the City of Tempe Construction Codes are applicable, to comply with this code and the City of Tempe Construction Codes.
(Ord. No. O2018.59, § 1, 8-30-18; Ord. No. O2026.24, § 14(Exh. C), 6-4-26)
Ask a question about Tempe law
Corpus searches the Tempe sections it holds and shows the ones that match, with their citations. Free, no sign-in.