§ 8.70.110 — Permit expiration, renewal and suspension

Municipal Code of the City of Jurupa Valley, California (Codified through Ordinance No. 2026-12, enacted October 1, 2026 (Supp. No. 28)) · Jurupa Valley Municipal Code § 8.70.110

Corpus is an independent public-information project, not the official City of Jurupa Valley website. Stable reference: corpuslaw.us/code/6c65543f-403c-4e14-af27-c32272e894e2

Sec. 8.70.110. - Permit expiration, renewal and suspension.

A. Issuance and completion of work. Every grading permit shall be valid for a period of one hundred eighty (180) days from the date of issuance. The Public Works Director may extend the one hundred eighty (180) day time period for up to three (3) successive periods of one hundred eighty (180) days each, upon written request by the permittee showing that circumstances beyond the control of the permittee have prevented completion of the grading. B. Suspension of construction or abandonment of work. Every grading permit shall expire by limitation and become null and void if the work authorized by the grading permit is not commenced within one hundred eighty (180) days from the original date of issuance. Every grading permit shall expire if the work authorized by such permit is suspended for a continuous period of one hundred eighty (180) days or if the site is abandoned at any time after work has commenced. C. Renewal. If a grading permit expires, upon written request and justification from the permittee within thirty (30) days of the expiration, the Public Works Director may renew the grading permit provided that the total elapsed time has not exceeded the time limits allowed for a grading permit under subsection A. of this section. D. Changed conditions. The Public Works Director may order the suspension of any work authorized by a grading permit upon determination that the weather, soil, slope or general site conditions may cause serious accelerated erosion or sediment damage either on-site or downstream from the site. Any suspension of work ordered by the Public Works Director shall toll the time limits applicable to the grading permit. E. Change of ownership. Grading permits shall automatically be suspended upon a change of ownership, until such time as the new owner obtains a new permit with the revised ownership information or until such time as the applicant provides new ownership information and a letter of consent for the grading operations from the new owner. There shall be no additional fee for the grading permit issued to the new owner, provided no changes to the approved plans are requested that generate additional staff work.

(Ord. No. 2019-17, § 2, 11-21-2019)

Ask a question about Jurupa Valley law

Corpus searches the Jurupa Valley sections it holds and shows the ones that match, with their citations. Free, no sign-in.