§ 8.70.300 — Grading inspection

Municipal Code of the City of Jurupa Valley, California (Codified through Ordinance No. 2026-12, enacted October 1, 2026 (Supp. No. 28)) · Jurupa Valley Municipal Code § 8.70.300

Corpus is an independent public-information project, not the official City of Jurupa Valley website. Stable reference: corpuslaw.us/code/03cb94c8-ef8c-4f74-80a9-ce0ddb06531e

Sec. 8.70.300. - Grading inspection.

A. Pre-grading and pre-paving meeting. Prior to any grading or clearing, brushing and grubbing there shall be a pre-grading meeting held on the site unless waived by the Public Works Director. Prior to placing concrete for curb and gutter, sidewalk, pavement base material or other similar improvement in the public right-of-way, there shall be a pre-paving meeting held on the site unless waived by the Public Works Director. The permittee shall notify the Public Works Director and request the meeting(s) at least two (2) working days prior to the meeting(s) and shall notify all principals responsible for grading or paving operations. B. Pre-work inspection. Prior to the commencement of any work authorized by a grading permit, the Public Works Director may inspect the site of the work to determine that the approved plans are current and reflect existing conditions. If the Public Works Director finds the soil or other conditions do not reflect the conditions shown on the approved plans or stated in the geotechnical reports, the Public Works Director may issue a stop work order until revised grading plans or modified geotechnical reports that reflect the actual site conditions have been submitted and approved by the Public Works Director. C. Site inspections. All work authorized under a grading permit shall be subject to the following inspections, where applicable, and the permittee shall provide notice to the Public Works Director at least one (1) working day prior to the work being ready for the inspection. (1) Excavation and fill inspection. All excavation and fill work shall be inspected as follows: (a) Canyon clean out. After all brush and unsuitable material is removed and an acceptable base is exposed, but before any fill is placed; (b) Toe bench and key. After the natural ground or bedrock is exposed and prepared to receive fill, but before fill is placed; (c) Over excavation. After the area is excavated but before fill is placed; (d) Excavation. After the excavation is started, but before the vertical depth of the excavation exceeds ten (10) feet and every ten (10) foot interval thereafter. (e) Fill. After the fill is started, but before the vertical height of the fill exceeds ten (10) feet and every ten (10) foot interval thereafter; (2) Concrete or gunite drainage device inspection. All concrete of gunite drainage devices shall be inspected as follows: (a) Alley gutter or concrete drainage device. After the sub-grade is prepared and any reinforcement placed but prior to concrete placement and then again after concrete placement; (b) Terrace drains, down drains, brow ditches. After grade is established but before placement of welded wire mesh or reinforcement and then again after placement of concrete or gunite. (3) Other drainage devices. Any subdrains, city storm drain or inlets or any earth swales shall be inspected as follows. (a) Subdrains. After excavation but prior to placement of filter materials and pipe. The subdrain pipe and filter material shall be on site for inspection. Inspection shall also occur after placement of pipe and filter material but before backfill. (b) City storm drains and inlets. After installation of form work and placement of reinforcement, but before concrete placement and then again after placement of concrete and removal of form work, but prior to backfilling. Inspection shall also occur after backfilling and completion of storm drain. (c) Earth swales. Prior to rough grading approval and then again prior to final grading approval. (4) Siltation control facilities (October 1 to May 31). All siltation control facilities shall be inspected as follows: (a) After excavation of desilting basins but prior to fill placement. Prefabricated drainage devices shall be available on-site for inspection; (b) After fill placement of desiltation basins but prior to placement of concrete or other non-erosive materials (if applicable); (c) After completion of an erosion control system in accordance with the approved erosion control plan and any requirements of the Public Works Director. (5) Rough grade inspection. All rough grading work shall be inspected when all rough grading is complete. Inspection shall occur after the Public Works Director has received, reviewed and approved the required geotechnical certification(s) and/or compaction reports and the civil engineer has submitted approval of line and grade on city approved format. Under normal circumstances, all subdrains and slope drains, if required, shall be in place and approved as a condition of rough grading inspection. (6) Paving inspection. All paving work shall be inspected as follows: (a) Subgrade. After subgrade is established, tested and approved by the soil engineer. The soil engineer may leave a field memo of compaction test results on site. The civil engineer shall provide approval of line and grade; (b) Base. After base course is in place, tested and approved by the soil engineer, but prior to prime coat and asphalt placement. The soil engineer may leave a field memo of compaction test results on site. Material invoices or weight tickets shall be required; (c) Asphalt concrete. During asphalt placement to verify compliance with the approved plans. Material invoices or weight tickets shall be required. Prior to application of seal coat, the paved surface shall be water tested to reveal any irregularities and shall be patched where required. (7) Special inspections. For special cases involving grading or paving related operations, the Public Works Director may establish special inspection requirements in accordance with the Uniform Building Code, latest Edition, Section 1701, as amended. Special cases may apply to work where, in the opinion of the Public Works Director, it is necessary to supplement the resources or expertise available for inspection. (8) Final inspection. All work shall undergo final inspection when all work, including the installation of all drainage structures and other protective devices, is complete and all written professional approvals and the required reports are submitted. D. Enforcement of inspections. (1) Whenever any work for which inspection is required, is covered or concealed by additional work without first being inspected, the Public Works Director may require, by written notice, that such work be exposed for examination. Any cost for exposing and recovering such non-inspected work shall be at the permittee's sole cost and expense. (2) The provisions of the Uniform Building Code (UBC), Section 104.2.4, Stop Orders, shall apply, whenever the Public Works Director determines that any work does not comply with the terms of the grading permit, the approved plans, any applicable provisions of this chapter or the code or state or federal law or that the soil or other conditions are not as stated on the grading permit, approved plans or geotechnical reports. Pursuant to such authority, the Public Works Director may order the work stopped by notice in writing served any person(s) engaged in doing or causing of such work to be done, and any such person(s) shall immediately stop such work until authorized by the Public Works Director to proceed with the work. E. Inspections by professionals of record. (1) The soil engineer shall be responsible for the professional inspection and approval concerning the preparation of ground to receive fills, testing for required compaction, stability of all finished slopes, design of buttress fills where required and incorporating data supplied by the engineering geologist. (2) The certified engineering geologist or professional geologist shall be responsible for the professional inspection and approval of the stability of cut slopes with respect to geological matters and the needs for subdrains or other ground water drainage devices. The certified engineering geologist or professional geologist shall report all findings to the soil engineer for engineering analysis. (3) When preliminary soil engineering reports are not required by the Public Works Director, inspection and testing may be required by a testing agency. The testing agency shall be responsible for the professional inspection and approval of cleared areas and benches to receive fill and the compaction of fills. (4) The Public Works Director, or his or her designee, shall inspect the project at various stages of work requiring approval and at any more frequent intervals necessary to determine that adequate inspection and testing are being completed by the professional consultants and to ensure conformance with the approved plans. F. Noncompliance; notification; corrective measures. If the civil engineer, the soil engineer, the engineering geologist or the testing agency finds during any inspection conducted pursuant to this chapter that the work is not being completed in conformance with the grading permit, the approved plans, any applicable provisions of this chapter or the code or state or federal law, the nonconformance shall be immediately reported in writing to the permittee, any contractor performing the work, the property owner and the Public Works Director. The civil engineer, the soil engineer, the engineering geologist or the testing agency shall submit recommendations for corrective measures to the Public Works Director for review and approval. The Public Works Director may require additional or revised soil engineering reports or engineering geology reports for approval of the corrective measures. G. Incorporation of corrective measures. The civil engineer shall incorporate any corrective measures approved by the Public Works Director into the approved plans, and the changes shall automatically be deemed to be made a part of the grading permit. The civil engineer of record during construction shall be responsible for establishing line and grade for the grading and drainage improvements and shall act as the coordinating agent in the event the need arises for liaison between the other professionals, the grading contractor and the Public Works Director. The civil engineer of record during construction shall also be responsible for preparing revised grading plans for review and approval, if required by the Public Works Director. Upon completion of the work, the submission of an as-built precise grading plan shall incorporate all corrective measures, changes and additions made during construction.

(Ord. No. 2019-17, § 2, 11-21-2019)