330.12

PERMIT APPROVAL BY OPERATION OF LAW

San Francisco Planning Code · SF Planning Code § 330.12

Corpus is an independent public-information project, not the official City of San Francisco website. Stable reference URL

SEC. 330.12. PERMIT APPROVAL BY OPERATION OF LAW. (a) If the Planning Department has failed to act on a Coastal Zone Permit Application within a one-year period from the date of which the application has been accepted as complete, the person claiming a right to proceed shall notify in writing the Zoning Administrator of his or her claim that the development has been approved by operation of law. Such notice shall specify the application which is claimed to be approved. (b) When an applicant claims that a Coastal Zone Permit Application has been approved by operation of law, a written notice shall be mailed by the Zoning Administrator within seven calendar days of such action to the California Coastal Commission and any person entitled to receive notice that the application has been approved by operation of law. Approval of a Coastal Zone Permit Application by expiration of time limitation may be appealed to the California Coastal Commission. (Ord. 509-85, App. 11/22/85; amended by Ord. 188-15 , File No. 150871, App. 11/4/2015, Eff. 12/4/2015) AMENDMENT HISTORY Nonsubstantive changes; Ord. 188-15 , Eff. 12/4/2015. SEC. 330.13. EFFECTIVE DATE OF APPROVED PROJECTS. (a) A final decision on an application for an appealable project shall become effective after a 10 working day appeal period to the California Coastal Commission has expired, unless either of the following occur: (1) a valid appeal is filed in accordance with City and State regulations, or (2) local government requirements are not met per Section 330.6(b). When either of